| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 9.00 | MTH |
17.00
| 16.00 | 1.00 | $500.00 | $500.00 |
| 13 | OFFICE FACILITIES | 9.00 | MTH |
17.00
| 15.50 | 1.50 | $2,500.00 | $3,750.00 |
| 19 | ROOT PRUNE TREE (INCL ROOT CONTROL BARRIER) | 7.00 | EA |
7.00
| 2.50 | 4.50 | $250.00 | $1,125.00 |
| 20 | CROWN REDUCTION, TREE (13" - 24" DIAMETER) | 3.00 | EA |
3.00
| 0.00 | 3.00 | $100.00 | $300.00 |
| 36 | PCC PAVEMENT | 480.00 | CY |
501.50
| 480.00 | 21.50 | $1,000.00 | $21,500.00 |
| 47 | JOINT SEAL, TYPE B | 64.00 | LF |
64.00
| 9.45 | 54.55 | $150.00 | $8,182.50 |
| 65 | GALVANIZED STEEL PICKET DOUBLE SWING GATE, 8' HIGH | 35.00 | LF |
35.00
| 30.00 | 5.00 | $501.40 | $2,507.00 |
| S-19 | ADDITIONAL PICKET FENCE | | LS |
1.00
| 0.95 | 0.05 | $75,000.00 | $3,750.00 |
| S-23 | COMPENSABLE DELAY COSTS | | WD |
29.00
| 0.00 | 29.00 | $1,500.00 | $43,500.00 |
| S-26 | UNCLASSIFIED EXCAVATION UNDER BRIDGE | | LS |
1.00
| 0.00 | 1.00 | $20,000.00 | $20,000.00 |
| S-27 | FURNISH BRIDGE DECK TREATMENT MATERIALS | | LS |
1.00
| 0.00 | 1.00 | $9,000.00 | $9,000.00 |
| S-28 | CLEAN CONCRETE DECK SURFACE | | LS |
1.00
| 0.00 | 1.00 | $32,000.00 | $32,000.00 |