| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 1 | CONSTRUCTION SCHEDULE (BASELINE) (STIPULATED UNIT PRICE OF $2,000) | 1.00 | LS |
1.00
| 0.00 | 1.00 | $2,000.00 | $2,000.00 |
| 8 | OFFICE FACILITIES | 7.00 | MTH |
1.00
| 0.00 | 1.00 | $4,500.00 | $4,500.00 |
| 9 | MOBILIZATION | 1.00 | LS |
0.25
| 0.00 | 0.25 | $100,000.00 | $25,000.00 |
| 21 | 30" DUAL WALL POLYPROPYLENE PIPE | 2,075.00 | LF |
807.00
| 0.00 | 807.00 | $265.00 | $213,855.00 |
| 22 | 36" DUAL WALL POLYPROPYLENE PIPE | 603.00 | LF |
110.00
| 0.00 | 110.00 | $275.00 | $30,250.00 |
| 23 | 48" DUAL WALL POLYPROPYLENE PIPE | 804.00 | LF |
300.00
| 0.00 | 300.00 | $438.00 | $131,400.00 |
| 34 | TRAFFIC CONTROL | 1.00 | LS |
0.25
| 0.00 | 0.25 | $30,000.00 | $7,500.00 |