| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 1 | CONSTRUCTION SCHEDULE (BASELINE) (STIPULATED UNIT PRICE OF $5,000) | 1.00 | LS |
1.00
| 1.00 | 0.00 | $5,000.00 | $0.00 |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 5.00 | MTH |
4.00
| 4.00 | 0.00 | $500.00 | $0.00 |
| 3 | CONSTRUCTION SCHEDULE (AS-BUILT) (STIPULATED UNIT PRICE OF $2,000) | 1.00 | LS |
1.00
| 0.00 | 1.00 | $2,000.00 | $2,000.00 |
| 4 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
1.00
| 1.00 | 0.00 | $5,500.00 | $0.00 |
| 5 | PREPARATION OF THE SITE-SPECIFIC HEALTH AND SAFETY PLAN (STIPULATED UNIT PRICE OF $3000) | 1.00 | LS |
1.00
| 1.00 | 0.00 | $3,000.00 | $0.00 |
| 6 | IMPLEMENTATION OF THE SITE-SPECIFIC HEALTH AND SAFETY PLAN | 1.00 | LS |
1.00
| 1.00 | 0.00 | $5,000.00 | $0.00 |
| 7 | PREPARATION OF THE SITE-SPECIFIC LEAD COMPLIANCE PLAN (STIPULATED UNIT PRICE OF $3000) | 1.00 | LS |
1.00
| 1.00 | 0.00 | $3,000.00 | $0.00 |
| 8 | IMPLEMENTATION OF THE SITE-SPECIFIC LEAD COMPLIANCE PLAN | 1.00 | LS |
1.00
| 1.00 | 0.00 | $15,000.00 | $0.00 |
| 9 | REMOVAL AND DISPOSAL OF LBP/LCP | 1.00 | LS |
1.00
| 1.00 | 0.00 | $51,000.00 | $0.00 |
| 10 | REMOVAL AND RECYCLING OF UNIVERSAL WASTE | 1.00 | LS |
1.00
| 1.00 | 0.00 | $1,000.00 | $0.00 |
| 11 | OFFICE FACILITIES | 6.00 | MTH |
5.00
| 5.00 | 0.00 | $1,000.00 | $0.00 |
| 12 | MOBILIZATION | 1.00 | LS |
1.00
| 1.00 | 0.00 | $171,000.00 | $0.00 |
| 13 | TEMPORARY WATER BARRIERS | 1.00 | LS |
1.00
| 1.00 | 0.00 | $120,000.00 | $0.00 |
| 14 | OPERATIONAL TEST | 1.00 | LS |
1.00
| 1.00 | 0.00 | $5,000.00 | $0.00 |
| 15 | MISCELLANEOUS MECHANICAL WORK | 1.00 | LS |
1.00
| 1.00 | 0.00 | $244,000.00 | $0.00 |
| 16 | 24" VERTICAL AXIAL FLOW PROPELLER PUMP WITH ELECTRIC MOTOR | 2.00 | EA |
2.00
| 2.00 | 0.00 | $183,500.00 | $0.00 |
| 17 | 36" VERTICAL AXIAL FLOW PROPELLER PUMP WITH RIGHT ANGLE GEAR DRIVE | 2.00 | EA |
2.00
| 2.00 | 0.00 | $211,000.00 | $0.00 |
| 18 | DISCHARGE LINES REPLACEMENT AND REHABILITATION | 1.00 | LS |
1.00
| 1.00 | 0.00 | $233,000.00 | $0.00 |
| 19 | FLAP GATES REFURBISHMENT | 1.00 | LS |
1.00
| 1.00 | 0.00 | $35,000.00 | $0.00 |
| 20 | CONCRETE COLLAR SUPPORTS | 1.00 | LS |
1.00
| 1.00 | 0.00 | $60,000.00 | $0.00 |
| 21 | FIBERGLASS REINFORCED POLYMER PLATFORM | 1.00 | LS |
1.00
| 1.00 | 0.00 | $40,000.00 | $0.00 |
| 22 | ELECTRICAL WORK | 1.00 | LS |
1.00
| 1.00 | 0.00 | $55,000.00 | $0.00 |
| S-1 | PUMP #3MODIFICATION | | LS |
0.9944
| 0.9944 | 0.00 | $10,000.00 | $0.00 |
| S-2 | $2" DRESSER COUPLING | | LS |
1.00
| 1.00 | 0.00 | $2,188.23 | $0.00 |
| S-3 | VICTAULIC COUPLING | | LS |
1.00
| 1.00 | 0.00 | $938.21 | $0.00 |
| S-4 | PLATFORM WALL BRACKET MODIFICATION | | LS |
1.00
| 1.00 | 0.00 | $17,850.00 | $0.00 |
| S-5 | PIPE SUPPORT DISCHARGE LINE 3 | | LS |
1.00
| 1.00 | 0.00 | $1,300.00 | $0.00 |
| S-6 | DISCHARGE PIPE COATING | | LS |
1.00
| 1.00 | 0.00 | $4,700.00 | $0.00 |
| S-7 | EXPLOSION PROOF SWITCH | | LS |
1.00
| 1.00 | 0.00 | $1,600.00 | $0.00 |
| S-8 | SOLID CONTAINMENT WALL (COFFERDAM) | | LS |
1.00
| 1.00 | 0.00 | $8,300.00 | $0.00 |
| S-9 | WET WELL CONCRETE REPAIR | | LS |
1.00
| 1.00 | 0.00 | $5,800.00 | $0.00 |
| S-10 | DISCHARGE LINE SLEEVES | | LS |
1.00
| 1.00 | 0.00 | $16,000.00 | $0.00 |
| S-11 | CONTRACT TIME EXTENSION | | WD |
12.00
| 12.00 | 0.00 | $0.00 | $0.00 |
| S-12 | SUM PUMP FLAP GATES | | LS |
1.00
| 1.00 | 0.00 | $1,600.00 | $0.00 |
| S-12A | CONTRACT TIME EXTENSION (FLAP GATE) | | WD |
0.00
| 0.00 | 0.00 | $0.00 | $0.00 |