| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 34.00 | MTH |
6.00
| 5.00 | 1.00 | $500.00 | $500.00 |
| 4 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
0.18
| 0.15 | 0.03 | $115,000.00 | $3,450.00 |
| 6 | IMPLEMENTATION OF THE SWPPP | 1.00 | LS |
0.18
| 0.15 | 0.03 | $300,000.00 | $9,000.00 |
| 12 | IMPLEMENTATION OF THE FUGITIVE DUST CONTROL PLAN | 34.00 | MTH |
6.00
| 5.00 | 1.00 | $8,000.00 | $8,000.00 |
| 15 | VEHICLES AND EQUIPMENT EMISSIONS REPORTING | 34.00 | MTH |
6.00
| 5.00 | 1.00 | $8,000.00 | $8,000.00 |
| 18 | NOISE MONITORING AND REPORTING | 34.00 | MTH |
6.00
| 5.00 | 1.00 | $6,000.00 | $6,000.00 |
| 20 | IMPLEMENTATION OF THE QUALITY CONTROL PROGRAM FOR MOISTURE CONTENT | 682.00 | DAY |
89.00
| 71.00 | 18.00 | $1,000.00 | $18,000.00 |
| 22 | OFFICE FACILITIES | 34.00 | MTH |
6.00
| 5.00 | 1.00 | $5,000.00 | $5,000.00 |
| 25 | MAINTENANCE OF TIRE WASHES | 90.00 | MTH |
12.00
| 10.00 | 2.00 | $3,500.00 | $7,000.00 |
| 26 | WATER TRUCKS | 682.00 | DAY |
112.00
| 93.00 | 19.00 | $1,500.00 | $28,500.00 |
| 27 | STREET SWEEPING | 682.00 | DAYS |
106.00
| 88.00 | 18.00 | $1,500.00 | $27,000.00 |
| 30 | MAINTENANCE OF TEMPORARY SOUND BARRIER | 5,800.00 | LF |
1,026.00
| 855.00 | 171.00 | $23.00 | $3,933.00 |
| 43 | CONCRETE REMOVAL (REINFORCED) | 523.00 | CY |
376.32
| 268.00 | 108.32 | $80.00 | $8,665.60 |
| 45 | BASIN EXCAVATION | 2,085,952.00 | CY |
74,038.00
| 41,597.00 | 32,441.00 | $2.30 | $74,614.30 |
| 46 | AGENCY EXCLUDES 2013 MODEL YEAR ENGINE TRUCK | 2,115,914.00 | TON |
320,058.48
| 249,343.73 | 70,714.75 | $0.01 | $707.15 |
| 47 | AGENCY EXCLUDES 2014 MODEL YEAR ENGINE TRUCK | 2,115,914.00 | TON |
273,505.57
| 208,762.72 | 64,742.85 | $0.01 | $647.43 |
| 48 | AGENCY EXCLUDES 2015 MODEL YEAR ENGINE TRUCK | 2,115,914.00 | TON |
201,456.80
| 153,948.62 | 47,508.18 | $0.01 | $475.08 |
| 49 | EXCAVATION, TRANSPORTATION AND DISPOSAL OF EXCESS BASIN MATERIAL | 1,343,403.00 | CY |
208,381.20
| 159,634.68 | 48,746.52 | $15.00 | $731,197.80 |
| 59 | STRUCTURE EXCAVATION (OVERFLOW STRUCTURE) | 7,761.00 | CY |
382.72
| 132.72 | 250.00 | $12.00 | $3,000.00 |
| 85 | REINFORCED CONCRETE OVERFLOW STRUCTURE NO. 1 | 1.00 | LS |
0.10
| 0.00 | 0.10 | $295,000.00 | $29,500.00 |
| 90 | REINFORCED CONCRETE OVERFLOW STRUCTURE NO. 6 | 1.00 | LS |
0.10
| 0.00 | 0.10 | $285,000.00 | $28,500.00 |
| 138 | TRAFFIC CONTROL | 1.00 | LS |
0.12
| 0.09 | 0.03 | $100,000.00 | $3,000.00 |
|