Los Angeles County Public Works
Project Management Division III
Progress Payment 36
Project Name: Mulholland Highway Over Triunfo Creek Bridge 1180 On-System, et al. (2018WOOLSEYFIRE)
Contractor: John S. Meek Company, Inc.
14732 South Maple Avenue
Gardena, CA 90248
Project ID: RDC0016358
Federal Number(s): ER - TBD
Original Contract: $2,124,824.00
Awarded: 1/31/2019
Period Ending: 4/6/2022
Board Accepted: 12/23/2019
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
S-16EXTENDED OFFICE FACILITY MTH 14.00 13.001.00$2,910.00$2,910.00
S-18MONTHLY OH COST TO KEEP JOB OPEN MTH 2.00 1.001.00$2,458.12$2,458.12

DEDUCTION DETAIL

There are NO deductions this period

FINANCIAL SUMMARY

  Total Previous Current
Earned $3,106,186.74 $3,100,818.62 $5,368.12
Retained $155,309.37 $155,040.96 $268.41
Deducted $0.00 $0.00 $0.00
Due $2,950,877.37 $2,945,777.66 $5,099.71



Contact Office Engineer
Chandra McLoud (626) 458-3165
Contractor Copy  
P Please consider the environment before printing this report.