Los Angeles County Public Works
Project Management Division III
As-Built 6
Project Name: Mulholland Highway at 300' S/O MM 3.71 Retaining Wall Off-Sys (2019FEBSTM1)
Contractor: Clarke Contracting Corporation
4646 Manhattan Beach Boulevard
Lawndale, CA 90260
Project ID: RDC0016408
Federal Number(s): None
Original Contract: $858,828.00
Awarded: 4/27/2021
Period Ending: 4/14/2022
Board Accepted: 4/20/2022
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
1CONSTRUCTION SCHEDULE (BASELINE) (STIPULATED UNIT PRICE OF $5,000)1.00LS 1.00 1.000.00$5,000.00$0.00
2CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH)3.00MTH 3.00 3.000.00$500.00$0.00
3CONSTRUCTION SCHEDULE (AS-BUILT) (STIPULATED UNIT PRICE OF $1,000)1.00LS 1.00 1.000.00$1,000.00$0.00
4IMPLEMENTATION OF BMPS1.00LS 1.00 1.000.00$5,000.00$0.00
5OFFICE FACILITIES4.00MTH 4.00 4.000.00$1,000.00$0.00
6MOBILIZATION1.00LS 1.00 1.000.00$80,000.00$0.00
7TRAFFIC CONTROL1.00LS 1.00 1.000.00$20,000.00$0.00
8CLEARING AND GRUBBING1.00LS 1.00 1.000.00$20,000.00$0.00
9TREE REMOVAL (6"-12" DIAMETER)4.00EA 4.00 4.000.00$400.00$0.00
10UNCLASSIFIED EXCAVATION78.00CY 78.00 78.000.00$200.00$0.00
11UNCLASSIFIED EXCAVATION (INVERTED SHOULDERS)12.00CY 12.00 12.000.00$200.00$0.00
12STRUCTURE EXCAVATION (RETAINING WALL)167.00CY 167.00 167.000.00$250.00$0.00
13STRUCTURE BACKFILL (RETAINING WALL)34.00CY 34.00 34.000.00$300.00$0.00
14NO. 3 CONCRETE AGGREGATE6.00CY 5.00 5.000.00$350.00$0.00
15TRENCH BACKFILL SLURRY (CLASS 100-E-100)52.00CY 52.00 52.000.00$150.00$0.00
16AC PAVEMENT24.00TON 27.45 27.450.00$500.00$0.00
17STRUCTURE CONCRETE (RETAINING WALL)53.00CY 53.00 53.000.00$2,795.00$0.00
18BAR REINFORCING STEEL8,000.00LB 8,000.00 8,000.000.00$5.00$0.00
19CABLE RAILING (CALTRANS STD PLAN B11-47)96.00LF 96.00 96.000.00$75.00$0.00
20CONST & REMOVE TEMP CHAIN LINK FENCE160.00LF 160.00 160.000.00$80.00$0.00
21STRUCTURE CONCRETE (CIDH PILES)90.00CY 90.00 90.000.00$490.00$0.00
22INSTALL STEEL PILE11.00EA 11.00 11.000.00$1,200.00$0.00
23DRILL PILE HOLES, 36" DIA561.00LF 492.00 492.000.00$98.00$0.00
24FURNISH STEEL PILES137,500.00LB 137,500.00 137,500.000.00$1.40$0.00
25MISCELLANEOUS METAL (RETAINING WALL)180.00LB 180.00 180.000.00$69.00$0.00
26PREFABRICATED DRAINAGE COMPOSITE960.00SF 960.00 960.000.00$14.00$0.00
27TIMBER LAGGING7.00MBF 7.00 7.000.00$3,500.00$0.00
28CONCRETE SURFACE TEXTURE865.00SF 865.00 865.000.00$8.00$0.00
29NON-WOVEN GEOTEXTILE FABRIC65.00SY 60.00 60.000.00$58.00$0.00
306" DIAMETER PVC PIPE, SCH 80125.00LF 125.00 125.000.00$78.00$0.00
31MIDWEST GUARDRAIL SYSTEM (STEEL POST W/ PLASTIC BLOCK)163.00LF 163.00 163.000.00$70.00$0.00
32IN-LINE TERMINAL SYSTEM (TYPE MSKT-SP-MGS)2.00EA 2.00 2.000.00$3,500.00$0.00
33SHOULDER GRADING333.00LF 333.00 333.000.00$27.00$0.00
34CONCRETE VEGETATION CONTROL (PER CALTRANS STD PLAN A77N5)15.00EA 15.00 15.000.00$475.00$0.00
35HMA DIKE PER CALTRANS STD PLAN A87B333.00LF 335.00 335.000.00$30.00$0.00
36DELINEATOR PER CALTRANS STD PLAN A77N411.00EA 10.00 10.000.00$59.00$0.00
S-1ADDITIONAL DRILLING COST LS 1.00 1.000.00$35,000.00$0.00

DEDUCTION DETAIL

There are NO deductions this period

FINANCIAL SUMMARY

  Total Previous Current
Earned $888,152.00 $888,152.00 $0.00
Retained $44,407.60 $44,407.60 $0.00
Deducted $0.00 $0.00 $0.00
Due $843,744.40 $843,744.40 $0.00



*The term "As-Built" used by the Department of Public Works in combination with the Engineer's Monthly Estimate process indicates that the project has been field accepted and that the pay quantities and deductions as detailed above are FINAL. Unless a certified letter is received by this office within 14 calendar days disputing the amounts shown, an acceptance letter will be filed with the Board of Supervisors authorizing the release of retention.