| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 34.00 | MTH |
7.00
| 6.00 | 1.00 | $500.00 | $500.00 |
| 4 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
0.21
| 0.18 | 0.03 | $115,000.00 | $3,450.00 |
| 6 | IMPLEMENTATION OF THE SWPPP | 1.00 | LS |
0.21
| 0.18 | 0.03 | $300,000.00 | $9,000.00 |
| 7 | SHORING OF OPEN EXCAVATIONS | 1.00 | LS |
0.10
| 0.00 | 0.10 | $200,000.00 | $20,000.00 |
| 12 | IMPLEMENTATION OF THE FUGITIVE DUST CONTROL PLAN | 34.00 | MTH |
7.00
| 6.00 | 1.00 | $8,000.00 | $8,000.00 |
| 15 | VEHICLES AND EQUIPMENT EMISSIONS REPORTING | 34.00 | MTH |
7.00
| 6.00 | 1.00 | $8,000.00 | $8,000.00 |
| 18 | NOISE MONITORING AND REPORTING | 34.00 | MTH |
7.00
| 6.00 | 1.00 | $6,000.00 | $6,000.00 |
| 20 | IMPLEMENTATION OF THE QUALITY CONTROL PROGRAM FOR MOISTURE CONTENT | 682.00 | DAY |
110.00
| 89.00 | 21.00 | $1,000.00 | $21,000.00 |
| 21 | CITY PERMIT AND INSPECTION FEES (ALLOWANCE OF $10,000) | 10,000.00 | AL |
28,117.63
| 1,110.02 | 27,007.61 | $1.00 | $27,007.61 |
| 22 | OFFICE FACILITIES | 34.00 | MTH |
7.00
| 6.00 | 1.00 | $5,000.00 | $5,000.00 |
| 25 | MAINTENANCE OF TIRE WASHES | 90.00 | MTH |
14.00
| 12.00 | 2.00 | $3,500.00 | $7,000.00 |
| 26 | WATER TRUCKS | 682.00 | DAY |
133.00
| 112.00 | 21.00 | $1,500.00 | $31,500.00 |
| 27 | STREET SWEEPING | 682.00 | DAYS |
127.00
| 106.00 | 21.00 | $1,500.00 | $31,500.00 |
| 30 | MAINTENANCE OF TEMPORARY SOUND BARRIER | 5,800.00 | LF |
1,197.00
| 1,026.00 | 171.00 | $23.00 | $3,933.00 |
| 35 | REMOVAL OF OIL PIPELINE | 1.00 | LS |
0.75
| 0.00 | 0.75 | $60,000.00 | $45,000.00 |
| 43 | CONCRETE REMOVAL (REINFORCED) | 523.00 | CY |
500.00
| 376.32 | 123.68 | $80.00 | $9,894.40 |
| 45 | BASIN EXCAVATION | 2,085,952.00 | CY |
134,226.00
| 74,038.00 | 60,188.00 | $2.30 | $138,432.40 |
| 46 | AGENCY EXCLUDES 2013 MODEL YEAR ENGINE TRUCK | 2,115,914.00 | TON |
401,314.73
| 320,058.48 | 81,256.25 | $0.01 | $812.56 |
| 47 | AGENCY EXCLUDES 2014 MODEL YEAR ENGINE TRUCK | 2,115,914.00 | TON |
345,535.97
| 273,505.57 | 72,030.40 | $0.01 | $720.30 |
| 48 | AGENCY EXCLUDES 2015 MODEL YEAR ENGINE TRUCK | 2,115,914.00 | TON |
253,785.11
| 201,456.80 | 52,328.31 | $0.01 | $523.28 |
| 49 | EXCAVATION, TRANSPORTATION AND DISPOSAL OF EXCESS BASIN MATERIAL | 1,343,403.00 | CY |
262,552.04
| 208,381.20 | 54,170.84 | $15.00 | $812,562.60 |
| 59 | STRUCTURE EXCAVATION (OVERFLOW STRUCTURE) | 7,761.00 | CY |
765.44
| 382.72 | 382.72 | $12.00 | $4,592.64 |
| 90 | REINFORCED CONCRETE OVERFLOW STRUCTURE NO. 6 | 1.00 | LS |
0.75
| 0.10 | 0.65 | $285,000.00 | $185,250.00 |
| 138 | TRAFFIC CONTROL | 1.00 | LS |
0.15
| 0.12 | 0.03 | $100,000.00 | $3,000.00 |
|