| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 13.00 | MTH |
13.00
| 12.00 | 1.00 | $500.00 | $500.00 |
| 4 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
1.00
| 0.96 | 0.04 | $2,000.00 | $80.00 |
| 5 | IMPLEMENTATION OF BMPS | 1.00 | LS |
1.00
| 0.96 | 0.04 | $20,000.00 | $800.00 |
| 6 | RESTORATION OF EXISTING IMPROVEMENTS | 1.00 | LS |
1.00
| 0.88 | 0.12 | $72,300.00 | $8,676.00 |
| 7 | SHORING OF OPEN EXCAVATIONS | 1.00 | LS |
1.00
| 0.96 | 0.04 | $3,110.00 | $124.40 |
| 9 | IMPLEMENTATION OF THE SITE-SPECIFIC HEALTH AND SAFETY PLAN | 1.00 | LS |
1.00
| 0.96 | 0.04 | $5,000.00 | $200.00 |
| 12 | OFFICE FACILITIES | 13.00 | MTH |
13.00
| 12.00 | 1.00 | $2,000.00 | $2,000.00 |
| 23 | AC PAVEMENT | 27.00 | TON |
27.00
| 0.00 | 27.00 | $220.00 | $5,940.00 |
| 35 | LANDSCAPING | 1.00 | LS |
1.00
| 0.92 | 0.08 | $81,355.00 | $6,508.40 |
| 36 | IRRIGATION SYSTEM | 1.00 | LS |
1.00
| 0.92 | 0.08 | $8,100.00 | $648.00 |
| 80 | ELECTRICAL WORK | 1.00 | LS |
1.00
| 0.86 | 0.14 | $751,723.00 | $105,241.22 |
| 82 | SYSTEM INTEGRATION | 1.00 | LS |
1.00
| 0.89 | 0.11 | $152,215.00 | $16,743.65 |