| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 6.00 | MTH |
1.00
| 0.00 | 1.00 | $500.00 | $500.00 |
| 4 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
0.30
| 0.00 | 0.30 | $5,000.00 | $1,500.00 |
| 5 | IMPLEMENTATION OF BMPS | 1.00 | LS |
0.30
| 0.00 | 0.30 | $10,000.00 | $3,000.00 |
| 7 | SHORING OF OPEN EXCAVATIONS | 1.00 | LS |
0.10
| 0.00 | 0.10 | $30,000.00 | $3,000.00 |
| 8 | OFFICE FACILITIES | 7.00 | MTH |
2.00
| 1.00 | 1.00 | $4,500.00 | $4,500.00 |
| 9 | MOBILIZATION | 1.00 | LS |
0.75
| 0.25 | 0.50 | $100,000.00 | $50,000.00 |
| 10 | TRENCH BACKFILL SLURRY (CLASS 100-E-100) | 1,541.00 | CY |
10.00
| 0.00 | 10.00 | $150.00 | $1,500.00 |
| 23 | 48" DUAL WALL POLYPROPYLENE PIPE | 804.00 | LF |
350.00
| 300.00 | 50.00 | $438.00 | $21,900.00 |
| 25 | SUPPORT FOR 8" OR LESS WATERLINE | 7.00 | EA |
1.00
| 0.00 | 1.00 | $3,000.00 | $3,000.00 |
| 34 | TRAFFIC CONTROL | 1.00 | LS |
0.35
| 0.25 | 0.10 | $30,000.00 | $3,000.00 |
| S-1 | EXTEND PART 1 NTP DURATION & PLAN REVISIONS DUE TO UTILITY CONFLICTS | | LS |
0.142
| 0.00 | 0.142 | $700,000.00 | $99,400.00 |
| S-2 | NON-WORKING DAYS | | NWD |
198.00
| 0.00 | 198.00 | $0.00 | $0.00 |