| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 8.00 | MTH |
2.00
| 1.00 | 1.00 | $500.00 | $500.00 |
| 4 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
0.22
| 0.11 | 0.11 | $4,000.00 | $440.00 |
| 5 | IMPLEMENTATION OF BMPS | 1.00 | LS |
0.22
| 0.11 | 0.11 | $15,000.00 | $1,650.00 |
| 7 | OFFICE FACILITIES | 9.00 | MTH |
2.00
| 1.00 | 1.00 | $1,500.00 | $1,500.00 |
| 12 | EXPLORATORY EXCAVATIONS OF UTILITIES (ALLOWANCE OF $15,000) | 15,000.00 | AL |
9,947.00
| 6,204.00 | 3,743.00 | $1.00 | $3,743.00 |
| 13 | NOISE CONTROL (ALLOWANCE OF $70,000) | 70,000.00 | AL |
53,580.00
| 21,685.00 | 31,895.00 | $1.00 | $31,895.00 |
| 42 | DRILL 42" DIAM HOLE | 125.00 | VF |
25.00
| 0.00 | 25.00 | $425.00 | $10,625.00 |
| 50 | GROUT 42" DIAM HOLE | 125.00 | VF |
25.00
| 0.00 | 25.00 | $293.00 | $7,325.00 |
| 60 | 36" DIAMETER CONDUCTOR STEEL CASING | 125.00 | VF |
25.00
| 0.00 | 25.00 | $676.00 | $16,900.00 |