| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 34.00 | MTH |
12.00
| 11.00 | 1.00 | $500.00 | $500.00 |
| 4 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
0.36
| 0.33 | 0.03 | $115,000.00 | $3,450.00 |
| 6 | IMPLEMENTATION OF THE SWPPP | 1.00 | LS |
0.36
| 0.33 | 0.03 | $300,000.00 | $9,000.00 |
| 12 | IMPLEMENTATION OF THE FUGITIVE DUST CONTROL PLAN | 34.00 | MTH |
12.00
| 11.00 | 1.00 | $8,000.00 | $8,000.00 |
| 15 | VEHICLES AND EQUIPMENT EMISSIONS REPORTING | 34.00 | MTH |
12.00
| 11.00 | 1.00 | $8,000.00 | $8,000.00 |
| 18 | NOISE MONITORING AND REPORTING | 34.00 | MTH |
12.00
| 11.00 | 1.00 | $6,000.00 | $6,000.00 |
| 20 | IMPLEMENTATION OF THE QUALITY CONTROL PROGRAM FOR MOISTURE CONTENT | 682.00 | DAY |
214.00
| 193.00 | 21.00 | $1,000.00 | $21,000.00 |
| 22 | OFFICE FACILITIES | 34.00 | MTH |
12.00
| 11.00 | 1.00 | $5,000.00 | $5,000.00 |
| 25 | MAINTENANCE OF TIRE WASHES | 90.00 | MTH |
24.00
| 22.00 | 2.00 | $3,500.00 | $7,000.00 |
| 26 | WATER TRUCKS | 682.00 | DAY |
238.00
| 217.00 | 21.00 | $1,500.00 | $31,500.00 |
| 27 | STREET SWEEPING | 682.00 | DAYS |
231.00
| 210.00 | 21.00 | $1,500.00 | $31,500.00 |
| 29 | CONSTRUCTION OF TEMPORARY SOUND BARRIER | 5,800.00 | LF |
5,670.81
| 5,646.81 | 24.00 | $210.00 | $5,040.00 |
| 30 | MAINTENANCE OF TEMPORARY SOUND BARRIER | 5,800.00 | LF |
2,052.00
| 1,881.00 | 171.00 | $23.00 | $3,933.00 |
| 43 | CONCRETE REMOVAL (REINFORCED) | 523.00 | CY |
523.00
| 500.00 | 23.00 | $80.00 | $1,840.00 |
| 45 | BASIN EXCAVATION | 2,085,952.00 | CY |
409,114.00
| 369,127.00 | 39,987.00 | $2.30 | $91,970.10 |
| 49 | EXCAVATION, TRANSPORTATION AND DISPOSAL OF EXCESS BASIN MATERIAL | 1,343,403.00 | CY |
528,624.76
| 474,468.37 | 54,156.39 | $15.00 | $812,345.85 |
| 55 | STRUCTURE EXCAVATION (INTAKE CANAL) | 3,768.00 | CY |
3,768.00
| 2,826.00 | 942.00 | $18.00 | $16,956.00 |
| 60 | STRUCTURE EXCAVATION (WEIR STRUCTURE EAST) | 65.00 | CY |
65.00
| 0.00 | 65.00 | $150.00 | $9,750.00 |
| 61 | STRUCTURE EXCAVATION (WEIR STRUCTURE WEST) | 65.00 | CY |
65.00
| 0.00 | 65.00 | $150.00 | $9,750.00 |
| 71 | AC PAVEMENT (TEMPORARY ACCESS ROAD AND RAMP) | 1,500.00 | TON |
1,399.48
| 1,355.48 | 44.00 | $115.00 | $5,060.00 |
| 72 | AC PAVEMENT (TEMPORARY ACCESS ROAD MAINTENANCE) | 1,500.00 | TON |
540.00
| 495.00 | 45.00 | $25.00 | $1,125.00 |
| 77 | REINFORCED CONCRETE BASIN EAST | 1.00 | LS |
0.50
| 0.00 | 0.50 | $400,000.00 | $200,000.00 |
| 78 | REINFORCED CONCRETE BASIN WEST | 1.00 | LS |
0.50
| 0.00 | 0.50 | $400,000.00 | $200,000.00 |
| 80 | REINFORCED CONCRETE OUTLET STRUCTURE | 7.00 | EA |
5.00
| 4.00 | 1.00 | $95,000.00 | $95,000.00 |
| 84 | REINFORCED CONCRETE OVERFLOW STRUCTURE WEST SETTLING BASIN | 1.00 | LS |
0.75
| 0.25 | 0.50 | $280,000.00 | $140,000.00 |
| 87 | REINFORCED CONCRETE OVERFLOW STRUCTURE NO. 3 | 1.00 | LS |
0.75
| 0.25 | 0.50 | $293,000.00 | $146,500.00 |
| 119 | 18" X 18" CAST-IRON SLIDE GATE ASSEMBLY | 2.00 | EA |
1.00
| 0.00 | 1.00 | $9,300.00 | $9,300.00 |
| 120 | 36" X 36" CAST-IRON SLIDE GATE ASSEMBLY | 8.00 | EA |
4.00
| 0.00 | 4.00 | $16,000.00 | $64,000.00 |
| 121 | 54" X 54" CAST-IRON SLIDE GATE ASSEMBLY | 4.00 | EA |
2.00
| 0.00 | 2.00 | $23,000.00 | $46,000.00 |
| 122 | 72" X 48" FABRICATED STAINLESS STEEL SLIDE GATE ASSEMBLY | 14.00 | EA |
7.00
| 0.00 | 7.00 | $20,000.00 | $140,000.00 |
| 123 | BEVEL GEAR OPERATOR | 24.00 | EA |
12.00
| 0.00 | 12.00 | $850.00 | $10,200.00 |
| 124 | MANUALLY OPERATED LIFT | 4.00 | EA |
2.00
| 0.00 | 2.00 | $1,500.00 | $3,000.00 |
| 125 | ELECTRIC MOTOR OPERATOR AND APPURTENANCES | 24.00 | EA |
12.00
| 0.00 | 12.00 | $7,800.00 | $93,600.00 |
| 138 | TRAFFIC CONTROL | 1.00 | LS |
0.30
| 0.27 | 0.03 | $100,000.00 | $3,000.00 |
| S-2 | CONCRETE REMOVAL (MESH REINFORCED) | | LS |
0.80
| 0.60 | 0.20 | $251,144.00 | $50,228.80 |
|