| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 8.00 | MTH |
4.00
| 3.00 | 1.00 | $500.00 | $500.00 |
| 4 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
0.44
| 0.33 | 0.11 | $4,000.00 | $440.00 |
| 5 | IMPLEMENTATION OF BMPS | 1.00 | LS |
0.44
| 0.33 | 0.11 | $15,000.00 | $1,650.00 |
| 7 | OFFICE FACILITIES | 9.00 | MTH |
4.00
| 3.00 | 1.00 | $1,500.00 | $1,500.00 |
| 12 | EXPLORATORY EXCAVATIONS OF UTILITIES (ALLOWANCE OF $15,000) | 15,000.00 | AL |
12,443.00
| 9,947.00 | 2,496.00 | $1.00 | $2,496.00 |
| 13 | NOISE CONTROL (ALLOWANCE OF $70,000) | 70,000.00 | AL |
70,000.00
| 65,100.00 | 4,900.00 | $1.00 | $4,900.00 |
| 34 | GEOPHYSICAL BOREHOLE LOG | 7.00 | EA |
1.00
| 0.00 | 1.00 | $11,988.00 | $11,988.00 |
| 35 | CALIPER LOG | 7.00 | EA |
1.00
| 0.00 | 1.00 | $9,435.00 | $9,435.00 |
| 37 | DRILL PILOT HOLE | 2,711.00 | VF |
567.00
| 485.00 | 82.00 | $578.00 | $47,396.00 |
| 41 | DRILL 30" DIAM HOLE | 1,335.00 | VF |
60.00
| 0.00 | 60.00 | $284.00 | $17,040.00 |
| 42 | DRILL 42" DIAM HOLE | 125.00 | VF |
75.00
| 50.00 | 25.00 | $425.00 | $10,625.00 |
| 50 | GROUT 42" DIAM HOLE | 125.00 | VF |
75.00
| 50.00 | 25.00 | $293.00 | $7,325.00 |
| 59 | 24" DIAMETER CONDUCTOR STEEL CASING | 50.00 | VF |
50.00
| 0.00 | 50.00 | $401.00 | $20,050.00 |
| 60 | 36" DIAMETER CONDUCTOR STEEL CASING | 125.00 | VF |
75.00
| 50.00 | 25.00 | $676.00 | $16,900.00 |
|