| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 6.00 | MTH |
6.00
| 5.00 | 1.00 | $500.00 | $500.00 |
| 4 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
0.912
| 0.90 | 0.012 | $5,000.00 | $60.00 |
| 6 | RESTORATION OF EXISTING IMPROVEMENTS | 1.00 | LS |
0.50
| 0.00 | 0.50 | $30,000.00 | $15,000.00 |
| 7 | SHORING OF OPEN EXCAVATIONS | 1.00 | LS |
0.90
| 0.85 | 0.05 | $30,000.00 | $1,500.00 |
| 8 | OFFICE FACILITIES | 7.00 | MTH |
7.00
| 6.00 | 1.00 | $4,500.00 | $4,500.00 |
| 10 | TRENCH BACKFILL SLURRY (CLASS 100-E-100) | 1,541.00 | CY |
1,307.0013
| 1,207.00 | 100.0013 | $150.00 | $15,000.20 |
| 18 | MANHOLE PER STD PLAN 322 (MOD) | 8.00 | EA |
6.00
| 5.00 | 1.00 | $11,000.00 | $11,000.00 |
| 21 | 30" DUAL WALL POLYPROPYLENE PIPE | 2,075.00 | LF |
1,671.00
| 1,396.00 | 275.00 | $265.00 | $72,875.00 |
| 29 | 18" CONCRETE COLLAR | 15.00 | EA |
7.00
| 6.00 | 1.00 | $2,000.00 | $2,000.00 |
| 32 | RESTORATION OF PERMANENT SURFACING | 1.00 | LS |
0.40
| 0.30 | 0.10 | $200,000.00 | $20,000.00 |
| 34 | TRAFFIC CONTROL | 1.00 | LS |
0.90
| 0.85 | 0.05 | $30,000.00 | $1,500.00 |
| S-1 | EXTEND PART 1 NTP DURATION & PLAN REVISIONS DUE TO UTILITY CONFLICTS | | LS |
0.9999
| 0.8571 | 0.1428 | $700,000.00 | $99,960.00 |
| S-6 | DELIVER 70 LF 36" HDPE PIPE | | LS |
0.50
| 0.00 | 0.50 | $8,829.15 | $4,414.58 |