Los Angeles County Public Works
Project Management Division III
Progress Payment 17
Project Name: Pacoima Spreading Grounds Basin Enhancement Project
Contractor: AMES CONSTRUCTION INC
2500 County Road 42 West
Burnsville , MN 55337
Project ID: FCC0001207
Federal Number(s): None
Original Contract: $54,483,460.00
Awarded: 5/6/2021
Period Ending: 12/20/2022
Board Accepted: 6/10/2025
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
2CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH)34.00MTH 15.00 14.001.00$500.00$500.00
4IMPLEMENTATION OF THE LTWHP1.00LS 0.45 0.420.03$115,000.00$3,450.00
6IMPLEMENTATION OF THE SWPPP1.00LS 0.45 0.420.03$300,000.00$9,000.00
12IMPLEMENTATION OF THE FUGITIVE DUST CONTROL PLAN34.00MTH 15.00 14.001.00$8,000.00$8,000.00
15VEHICLES AND EQUIPMENT EMISSIONS REPORTING34.00MTH 15.00 14.001.00$8,000.00$8,000.00
18NOISE MONITORING AND REPORTING34.00MTH 15.00 14.001.00$6,000.00$6,000.00
20IMPLEMENTATION OF THE QUALITY CONTROL PROGRAM FOR MOISTURE CONTENT682.00DAY 269.00 252.0017.00$1,000.00$17,000.00
22OFFICE FACILITIES34.00MTH 15.00 14.001.00$5,000.00$5,000.00
25MAINTENANCE OF TIRE WASHES90.00MTH 30.00 28.002.00$3,500.00$7,000.00
26WATER TRUCKS682.00DAY 297.00 277.0020.00$1,500.00$30,000.00
27STREET SWEEPING682.00DAYS 288.00 269.0019.00$1,500.00$28,500.00
29CONSTRUCTION OF TEMPORARY SOUND BARRIER5,800.00LF 5,742.81 5,718.8124.00$210.00$5,040.00
30MAINTENANCE OF TEMPORARY SOUND BARRIER5,800.00LF 2,565.00 2,394.00171.00$23.00$3,933.00
44UNCLASSIFIED EXCAVATION13,881.00CY 11,149.80 5,341.005,808.80$9.00$52,279.20
45BASIN EXCAVATION2,085,952.00CY 589,080.00 515,801.0073,279.00$2.30$168,541.70
49EXCAVATION, TRANSPORTATION AND DISPOSAL OF EXCESS BASIN MATERIAL1,343,403.00CY 671,127.06 626,577.1844,549.88$15.00$668,248.20
57STRUCTURE EXCAVATION (OUTFALL STRUCTURE FOR EAST SETTLING BASIN)61.00CY 61.00 0.0061.00$160.00$9,760.00
58STRUCTURE EXCAVATION (OUTFALL STRUCTURE FOR WEST SETTLING BASIN)42.00CY 42.00 0.0042.00$235.00$9,870.00
71AC PAVEMENT (TEMPORARY ACCESS ROAD AND RAMP)1,500.00TON 1,500.00 1,487.4812.52$115.00$1,439.80
72AC PAVEMENT (TEMPORARY ACCESS ROAD MAINTENANCE)1,500.00TON 675.00 630.0045.00$25.00$1,125.00
76REINFORCED CONCRETE ACCESS RAMP160.00CY 160.00 148.5011.50$1,600.00$18,400.00
105EXPANDED METAL CAGE ENCLOSURE FOR LOW FLOW AND CONCRETE LINED BASINS3.00EA 1.50 0.001.50$30,000.00$45,000.00
1098' - 6" W X 3' - 0" H DBL RCB128.00LF 45.00 0.0045.00$2,100.00$94,500.00
138TRAFFIC CONTROL1.00LS 0.39 0.360.03$100,000.00$3,000.00
S-2CONCRETE REMOVAL (MESH REINFORCED) LS 0.95 0.800.15$251,144.00$37,671.60
S-5ASHORING AT EAST SIDE OF INTAKE CHANNEL LS 1.00 0.750.25$193,059.30$48,264.83

DEDUCTION DETAIL

There are NO deductions this period

FINANCIAL SUMMARY

  Total Previous Current
Earned $26,159,732.04 $24,870,208.71 $1,289,523.33
Retained $1,307,986.62 $1,243,510.45 $64,476.17
Deducted $0.00 $0.00 $0.00
Due $24,851,745.42 $23,626,698.26 $1,225,047.16