Los Angeles County Public Works
Project Management Division III
Progress Payment 8
Project Name: Hacienda Channel - La Plata Avenue Drain
Contractor: Mladen Buntich Construction Company, Inc.
1500 West Ninth Street
Upland, CA 91786-5636
Project ID: FCC0001332
Federal Number(s): None
Original Contract: $2,292,502.00
Awarded: 5/17/2021
Period Ending: 1/6/2023
Board Accepted: 7/11/2023
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
4IMPLEMENTATION OF THE LTWHP1.00LS 0.962 0.9120.05$5,000.00$250.00
5IMPLEMENTATION OF BMPS1.00LS 0.95 0.900.05$10,000.00$500.00
6RESTORATION OF EXISTING IMPROVEMENTS1.00LS 0.90 0.500.40$30,000.00$12,000.00
7SHORING OF OPEN EXCAVATIONS1.00LS 1.00 0.900.10$30,000.00$3,000.00
10TRENCH BACKFILL SLURRY (CLASS 100-E-100)1,541.00CY 1,511.0013 1,307.0013204.00$150.00$30,600.00
14JUNCTION STRUCTURE PER DETAIL E8.00EA 8.00 4.004.00$6,000.00$24,000.00
15JUNCTION STRUCTURE PER DETAIL F4.00EA 4.00 2.002.00$6,000.00$12,000.00
18MANHOLE PER STD PLAN 322 (MOD)8.00EA 8.00 6.002.00$11,000.00$22,000.00
2130" DUAL WALL POLYPROPYLENE PIPE2,075.00LF 2,075.00 1,671.00404.00$265.00$107,060.00
24SUPPORT FOR 15" OR LESS WATERLINE4.00EA 2.00 1.001.00$3,000.00$3,000.00
2918" CONCRETE COLLAR15.00EA 15.00 7.008.00$2,000.00$16,000.00
32RESTORATION OF PERMANENT SURFACING1.00LS 0.60 0.400.20$200,000.00$40,000.00
33ABANDON EXISTING MANHOLE3.00EA 3.00 0.003.00$2,000.00$6,000.00
34TRAFFIC CONTROL1.00LS 0.95 0.900.05$30,000.00$1,500.00
S-6DELIVER 70 LF 36" HDPE PIPE LS 1.00 0.500.50$8,829.15$4,414.58

DEDUCTION DETAIL

There are NO deductions this period

FINANCIAL SUMMARY

  Total Previous Current
Earned $2,737,182.36 $2,454,857.78 $282,324.58
Retained $136,859.12 $122,742.89 $14,116.23
Deducted $0.00 $0.00 $0.00
Due $2,600,323.24 $2,332,114.89 $268,208.35



Contact Office Engineer
Contractor Copy  