| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 34.00 | MTH |
17.00
| 16.00 | 1.00 | $500.00 | $500.00 |
| 4 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
0.51
| 0.48 | 0.03 | $115,000.00 | $3,450.00 |
| 6 | IMPLEMENTATION OF THE SWPPP | 1.00 | LS |
0.51
| 0.48 | 0.03 | $300,000.00 | $9,000.00 |
| 7 | SHORING OF OPEN EXCAVATIONS | 1.00 | LS |
0.75
| 0.50 | 0.25 | $200,000.00 | $50,000.00 |
| 12 | IMPLEMENTATION OF THE FUGITIVE DUST CONTROL PLAN | 34.00 | MTH |
17.00
| 16.00 | 1.00 | $8,000.00 | $8,000.00 |
| 15 | VEHICLES AND EQUIPMENT EMISSIONS REPORTING | 34.00 | MTH |
17.00
| 16.00 | 1.00 | $8,000.00 | $8,000.00 |
| 18 | NOISE MONITORING AND REPORTING | 34.00 | MTH |
17.00
| 16.00 | 1.00 | $6,000.00 | $6,000.00 |
| 20 | IMPLEMENTATION OF THE QUALITY CONTROL PROGRAM FOR MOISTURE CONTENT | 682.00 | DAY |
298.00
| 280.00 | 18.00 | $1,000.00 | $18,000.00 |
| 22 | OFFICE FACILITIES | 34.00 | MTH |
17.00
| 16.00 | 1.00 | $5,000.00 | $5,000.00 |
| 25 | MAINTENANCE OF TIRE WASHES | 90.00 | MTH |
34.00
| 32.00 | 2.00 | $3,500.00 | $7,000.00 |
| 26 | WATER TRUCKS | 682.00 | DAY |
330.00
| 310.00 | 20.00 | $1,500.00 | $30,000.00 |
| 27 | STREET SWEEPING | 682.00 | DAYS |
320.00
| 300.00 | 20.00 | $1,500.00 | $30,000.00 |
| 29 | CONSTRUCTION OF TEMPORARY SOUND BARRIER | 5,800.00 | LF |
5,790.81
| 5,766.81 | 24.00 | $210.00 | $5,040.00 |
| 30 | MAINTENANCE OF TEMPORARY SOUND BARRIER | 5,800.00 | LF |
2,907.00
| 2,736.00 | 171.00 | $23.00 | $3,933.00 |
| 45 | BASIN EXCAVATION | 2,085,952.00 | CY |
725,265.00
| 627,996.00 | 97,269.00 | $2.30 | $223,718.70 |
| 49 | EXCAVATION, TRANSPORTATION AND DISPOSAL OF EXCESS BASIN MATERIAL | 1,343,403.00 | CY |
746,434.51
| 695,144.56 | 51,289.95 | $15.00 | $769,349.25 |
| 72 | AC PAVEMENT (TEMPORARY ACCESS ROAD MAINTENANCE) | 1,500.00 | TON |
765.00
| 720.00 | 45.00 | $25.00 | $1,125.00 |
| 74 | CONCRETE DOWN DRAIN INLET | 30.00 | CY |
9.00
| 0.00 | 9.00 | $3,000.00 | $27,000.00 |
| 81 | REINFORCED CONCRETE OUTLET STRUCTURE FOR EAST SETTLING BASIN | 1.00 | LS |
0.75
| 0.50 | 0.25 | $61,000.00 | $15,250.00 |
| 82 | REINFORCED CONCRETE OUTLET STRUCTURE FOR WEST SETTLING BASIN | 1.00 | LS |
0.75
| 0.50 | 0.25 | $62,000.00 | $15,500.00 |
| 84 | REINFORCED CONCRETE OVERFLOW STRUCTURE WEST SETTLING BASIN | 1.00 | LS |
0.80
| 0.75 | 0.05 | $280,000.00 | $14,000.00 |
| 106 | EXPANDED METAL CAGE ENCLOSURE FOR REINFORCED CONCRETE OVERFLOW STRUCTURE | 8.00 | EA |
6.00
| 4.00 | 2.00 | $25,000.00 | $50,000.00 |
| 109 | 8' - 6" W X 3' - 0" H DBL RCB | 128.00 | LF |
128.00
| 45.00 | 83.00 | $2,100.00 | $174,300.00 |
| 120 | 36" X 36" CAST-IRON SLIDE GATE ASSEMBLY | 8.00 | EA |
6.00
| 5.00 | 1.00 | $16,000.00 | $16,000.00 |
| 123 | BEVEL GEAR OPERATOR | 24.00 | EA |
18.00
| 12.00 | 6.00 | $850.00 | $5,100.00 |
| 125 | ELECTRIC MOTOR OPERATOR AND APPURTENANCES | 24.00 | EA |
18.00
| 12.00 | 6.00 | $7,800.00 | $46,800.00 |
| 138 | TRAFFIC CONTROL | 1.00 | LS |
0.45
| 0.42 | 0.03 | $100,000.00 | $3,000.00 |
| S-8 | REMOVE 3 ADDITIONAL TREES (DIAM > 16") | | LS |
1.00
| 0.00 | 1.00 | $12,600.00 | $12,600.00 |
|