Los Angeles County Public Works
Project Management Division III
Progress Payment 9
Project Name: Hacienda Channel - La Plata Avenue Drain
Contractor: Mladen Buntich Construction Company, Inc.
1500 West Ninth Street
Upland, CA 91786-5636
Project ID: FCC0001332
Federal Number(s): None
Original Contract: $2,292,502.00
Awarded: 5/17/2021
Period Ending: 3/6/2023
Board Accepted: 7/11/2023
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
4IMPLEMENTATION OF THE LTWHP1.00LS 1.00 0.9620.038$5,000.00$190.00
5IMPLEMENTATION OF BMPS1.00LS 1.00 0.950.05$10,000.00$500.00
6RESTORATION OF EXISTING IMPROVEMENTS1.00LS 1.00 0.900.10$30,000.00$3,000.00
32RESTORATION OF PERMANENT SURFACING1.00LS 1.00 0.600.40$200,000.00$80,000.00
34TRAFFIC CONTROL1.00LS 1.00 0.950.05$30,000.00$1,500.00
S-1EXTEND PART 1 NTP DURATION & PLAN REVISIONS DUE TO UTILITY CONFLICTS LS 1.00 0.99990.0001$700,000.00$70.00

DEDUCTION DETAIL

There are NO deductions this period

FINANCIAL SUMMARY

  Total Previous Current
Earned $2,822,442.36 $2,737,182.36 $85,260.00
Retained $141,122.12 $136,859.12 $4,263.00
Deducted $0.00 $0.00 $0.00
Due $2,681,320.24 $2,600,323.24 $80,997.00