Los Angeles County Public Works
Project Management Division III
Progress Payment 3
Project Name: Castaic Road at Ridge Route Road and The Old Road at Parker Rd
Contractor: Elecnor Belco Electric, Inc.
14320 Albers Way
Chino, CA 91710
Project ID: TDS0001703
Federal Number(s): None
Original Contract: $1,951,442.00
Awarded: 12/20/2022
Period Ending: 5/4/2023
Board Accepted: 6/30/2025
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
5IMPLEMENTATION OF BMPS1.00LS 1.00 0.750.25$5,000.00$1,250.00
6MOBILIZATION1.00LS 0.75 0.500.25$200,000.00$50,000.00
7CONCRETE REMOVAL (NON-REINFORCED)3.00CY 3.00 0.003.00$1,400.00$4,200.00
9UNCLASSIFIED EXCAVATION584.00CY 308.12 0.00308.12$75.00$23,109.00
10CRUSHED MISCELLANEOUS BASE374.00CY 123.62 0.00123.62$162.00$20,026.44
15CONCRETE BUS PAD19.00CY 19.00 0.0019.00$1,400.00$26,600.00
17PCC CURB & GUTTER, TYPE A2-8449.00LF 412.00 0.00412.00$115.00$47,380.00
18PCC WALK & DRIVEWAYS, 4" THICK2,359.00SF 2,359.00 0.002,359.00$25.00$58,975.00
19PCC CURB RAMPS29.00CY 25.09 0.0025.09$1,400.00$35,126.00
20DETECTABLE WARNING SURFACE63.00SF 60.00 0.0060.00$90.00$5,400.00
21RELOCATE EXISTING BUS SHELTER1.00EA 1.00 0.001.00$7,000.00$7,000.00
22RELOCATE EXISTING MAILBOX1.00EA 1.00 0.001.00$2,200.00$2,200.00
23RELOCATE TRASH RECEPTACLE1.00EA 1.00 0.001.00$2,200.00$2,200.00
24REMOVE SLIDING GATE34.00LF 34.00 0.0034.00$85.00$2,890.00
25REMOVE CHAIN LINK FENCE 5' HIGH WITH BARBED WIRE24.00LF 10.00 0.0010.00$85.00$850.00
35TYPE 332 CABINET FOUNDATION2.00EA 2.00 1.001.00$4,000.00$4,000.00
44PEDESTRIAN PUSH BUTTON POST FOUNDATION2.00EA 1.00 0.001.00$1,500.00$1,500.00
45TYPE 15 STANDARD FOUNDATION8.00EA 8.00 5.003.00$4,500.00$13,500.00
46TYPE 24 STANDARD FOUNDATION2.00EA 2.00 0.002.00$6,500.00$13,000.00
47TYPE 26 STANDARD FOUNDATION2.00EA 1.00 0.001.00$6,500.00$6,500.00
48TYPE 29 STANDARD FOUNDATION4.00EA 3.00 1.002.00$7,000.00$14,000.00
661" CONDUIT (SCH 80 PVC)100.00LF 16.00 0.0016.00$120.00$1,920.00
673" CONDUIT (SCH 80 PVC)750.00LF 698.00 643.0055.00$150.00$8,250.00
74INSTALL COMPOSITE TYPE 3 PULL BOX INCL COVER18.00EA 18.00 10.008.00$1,400.00$11,200.00
98TRAFFIC CONTROL1.00LS 0.25 0.000.25$80,000.00$20,000.00

DEDUCTION DETAIL

There are NO deductions this period

FINANCIAL SUMMARY

  Total Previous Current
Earned $693,876.44 $312,800.00 $381,076.44
Retained $34,693.82 $15,640.00 $19,053.82
Deducted $0.00 $0.00 $0.00
Due $659,182.62 $297,160.00 $362,022.62