| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 34.00 | MTH |
20.00
| 19.00 | 1.00 | $500.00 | $500.00 |
| 4 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
0.60
| 0.57 | 0.03 | $115,000.00 | $3,450.00 |
| 6 | IMPLEMENTATION OF THE SWPPP | 1.00 | LS |
0.60
| 0.57 | 0.03 | $300,000.00 | $9,000.00 |
| 12 | IMPLEMENTATION OF THE FUGITIVE DUST CONTROL PLAN | 34.00 | MTH |
20.00
| 19.00 | 1.00 | $8,000.00 | $8,000.00 |
| 15 | VEHICLES AND EQUIPMENT EMISSIONS REPORTING | 34.00 | MTH |
20.00
| 19.00 | 1.00 | $8,000.00 | $8,000.00 |
| 18 | NOISE MONITORING AND REPORTING | 34.00 | MTH |
20.00
| 19.00 | 1.00 | $6,000.00 | $6,000.00 |
| 20 | IMPLEMENTATION OF THE QUALITY CONTROL PROGRAM FOR MOISTURE CONTENT | 682.00 | DAY |
348.00
| 329.00 | 19.00 | $1,000.00 | $19,000.00 |
| 22 | OFFICE FACILITIES | 34.00 | MTH |
20.00
| 19.00 | 1.00 | $5,000.00 | $5,000.00 |
| 25 | MAINTENANCE OF TIRE WASHES | 90.00 | MTH |
43.00
| 40.00 | 3.00 | $3,500.00 | $10,500.00 |
| 26 | WATER TRUCKS | 682.00 | DAY |
381.00
| 362.00 | 19.00 | $1,500.00 | $28,500.00 |
| 27 | STREET SWEEPING | 682.00 | DAYS |
371.00
| 351.00 | 20.00 | $1,500.00 | $30,000.00 |
| 30 | MAINTENANCE OF TEMPORARY SOUND BARRIER | 5,800.00 | LF |
3,420.00
| 3,249.00 | 171.00 | $23.00 | $3,933.00 |
| 45 | BASIN EXCAVATION | 2,085,952.00 | CY |
893,000.00
| 808,439.00 | 84,561.00 | $2.30 | $194,490.30 |
| 49 | EXCAVATION, TRANSPORTATION AND DISPOSAL OF EXCESS BASIN MATERIAL | 1,343,403.00 | CY |
867,294.88
| 822,627.98 | 44,666.90 | $15.00 | $670,003.50 |
| 67 | CRUSHED MISCELLANEOUS BASE | 9,805.00 | CY |
6,590.00
| 1,960.00 | 4,630.00 | $50.00 | $231,500.00 |
| 72 | AC PAVEMENT (TEMPORARY ACCESS ROAD MAINTENANCE) | 1,500.00 | TON |
900.00
| 855.00 | 45.00 | $25.00 | $1,125.00 |
| 107 | EXPANDED METAL CAGE ENCLOSURE FOR WEIR | 2.00 | EA |
1.79
| 0.00 | 1.79 | $105,000.00 | $187,950.00 |
| 116 | JACK 72" RUBBER GASKETED RCP, 3000 D | 427.00 | LF |
304.00
| 192.00 | 112.00 | $1,300.00 | $145,600.00 |
| 129 | 4" WATERMAIN, .14" THICK STL | 130.00 | LF |
81.00
| 65.00 | 16.00 | $500.00 | $8,000.00 |
| 137 | ELECTRICAL WORK | 1.00 | LS |
0.65
| 0.60 | 0.05 | $920,000.00 | $46,000.00 |
| 138 | TRAFFIC CONTROL | 1.00 | LS |
0.54
| 0.51 | 0.03 | $100,000.00 | $3,000.00 |
| 139 | FLASHING ARROW SIGN | 2.00 | EA |
2.00
| 1.00 | 1.00 | $1,000.00 | $1,000.00 |
|