| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 1 | CONSTRUCTION SCHEDULE (BASELINE) (STIPULATED UNIT PRICE OF $2,500) | 1.00 | LS |
1.00
| 0.00 | 1.00 | $2,500.00 | $2,500.00 |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 6.00 | MTH |
1.00
| 0.00 | 1.00 | $500.00 | $500.00 |
| 4 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
0.14
| 0.00 | 0.14 | $35,000.00 | $4,900.00 |
| 5 | IMPLEMENTATION OF BMPS | 1.00 | LS |
0.14
| 0.00 | 0.14 | $35,000.00 | $4,900.00 |
| 7 | PREPARATION OF THE SITE-SPECIFIC HEALTH AND SAFETY PLAN (STIPULATED UNIT PRICE OF $3000) | 1.00 | LS |
1.00
| 0.00 | 1.00 | $3,000.00 | $3,000.00 |
| 8 | IMPLEMENTATION OF THE SITE-SPECIFIC HEALTH AND SAFETY PLAN | 1.00 | LS |
0.14
| 0.00 | 0.14 | $35,000.00 | $4,900.00 |
| 12 | OFFICE FACILITIES | 7.00 | MTH |
1.00
| 0.00 | 1.00 | $5,000.00 | $5,000.00 |
| 13 | MOBILIZATION | 1.00 | LS |
0.50
| 0.00 | 0.50 | $200,000.00 | $100,000.00 |
| 14 | CLEARING AND GRUBBING | 1.00 | LS |
0.14
| 0.00 | 0.14 | $150,000.00 | $21,000.00 |
| 26 | 0.5 MG WATER STORAGE TANK AND APPURTENANCES | 1.00 | LS |
0.096
| 0.00 | 0.096 | $2,400,000.00 | $230,400.00 |
| 31 | 1250 GAL BLADDER SURGE TANK CONTROL SYSTEM | 1.00 | LS |
0.15
| 0.00 | 0.15 | $100,000.00 | $15,000.00 |
| 32 | 3000 GAL BLADDER SURGE TANK CONTROL SYSTEM | 1.00 | LS |
0.15
| 0.00 | 0.15 | $100,000.00 | $15,000.00 |
| 36 | CONCRETE PAVING (PCC) 4" THICK | 305.00 | SF |
30.50
| 0.00 | 30.50 | $50.00 | $1,525.00 |
| 37 | TREE PROTECTION | 1.00 | LS |
1.00
| 0.00 | 1.00 | $5,000.00 | $5,000.00 |
| 38 | ELECTRICAL WORK | 1.00 | LS |
0.05
| 0.00 | 0.05 | $550,000.00 | $27,500.00 |
| 39 | TRAFFIC CONTROL | 1.00 | LS |
0.10
| 0.00 | 0.10 | $25,000.00 | $2,500.00 |
| 40 | CONST & REMOVE TEMP CHAIN LINK FENCE | 275.00 | LF |
137.50
| 0.00 | 137.50 | $50.00 | $6,875.00 |
| S-1 | TIME EXTENSION | | WD |
31.00
| 0.00 | 31.00 | $0.00 | $0.00 |