| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 2.00 | MTH |
1.00
| 0.00 | 1.00 | $500.00 | $500.00 |
| 6 | MOBILIZATION | 1.00 | LS |
1.00
| 0.75 | 0.25 | $200,000.00 | $50,000.00 |
| 25 | REMOVE CHAIN LINK FENCE 5' HIGH WITH BARBED WIRE | 24.00 | LF |
22.00
| 10.00 | 12.00 | $85.00 | $1,020.00 |
| 26 | CHAIN LINK FENCE, 6' HIGH | 46.00 | LF |
26.00
| 0.00 | 26.00 | $400.00 | $10,400.00 |
| 27 | 34' CHAIN LINK SLIDING GATE | 1.00 | EA |
1.00
| 0.00 | 1.00 | $11,000.00 | $11,000.00 |
| 28 | HEAVY DUTY COMMERCIAL SLIDE GATE OPENER (1 HP MINIMUM, RATED FOR GATES UP TO 50 FT IN LENGTH AND 1500 POUNDS), BATTERY BACKUP, GATE SAFETY SENSORS, 2 KEY PADS, 20 REMOTE CONTROLLERS. | 1.00 | EA |
1.00
| 0.00 | 1.00 | $110,000.00 | $110,000.00 |
| 29 | GRADE BEAM WITH 2" V-TRACK AND J-BOLTS | 68.00 | LF |
38.00
| 0.00 | 38.00 | $300.00 | $11,400.00 |
| 30 | 5' PEDESTRIAN WALK GATE DOOR/ACCESS WITH KEYPAD LOCK | 1.00 | EA |
1.00
| 0.00 | 1.00 | $15,000.00 | $15,000.00 |
| 31 | KEY PAD STATION WITH GOOSE NECK POST | 2.00 | EA |
1.00
| 0.00 | 1.00 | $5,000.00 | $5,000.00 |
| 32 | GOOSE NECK POST FOUNDATION | 2.00 | EA |
1.00
| 0.00 | 1.00 | $5,000.00 | $5,000.00 |
| 34 | INSTALL TYPE 332 CABINET COMPLETE W/ 2070 CONTROLLER | 2.00 | EA |
2.00
| 0.00 | 2.00 | $55,000.00 | $110,000.00 |
| 36 | INSTALL TYPE III-BF SERVICE CABINET | 2.00 | EA |
2.00
| 0.00 | 2.00 | $11,000.00 | $22,000.00 |
| 37 | TYPE III-B SERVICE CABINET FOUNDATION | 2.00 | EA |
2.00
| 0.00 | 2.00 | $4,000.00 | $8,000.00 |
| 39 | PEDESTRIAN PUSH BUTTON POST | 2.00 | EA |
1.00
| 0.00 | 1.00 | $700.00 | $700.00 |
| 40 | INSTALL TYPE 15TS STANDARD | 8.00 | EA |
8.00
| 0.00 | 8.00 | $2,500.00 | $20,000.00 |
| 41 | INSTALL TYPE 24 STANDARD | 2.00 | EA |
2.00
| 0.00 | 2.00 | $2,500.00 | $5,000.00 |
| 42 | INSTALL TYPE 26 STANDARD | 2.00 | EA |
1.00
| 0.00 | 1.00 | $3,000.00 | $3,000.00 |
| 43 | INSTALL TYPE 29 STANDARD | 4.00 | EA |
3.00
| 0.00 | 3.00 | $3,000.00 | $9,000.00 |
| 49 | INSTALL 30' SIGNAL MAST ARM | 2.00 | EA |
2.00
| 0.00 | 2.00 | $900.00 | $1,800.00 |
| 50 | INSTALL 35' SIGNAL MAST ARM | 2.00 | EA |
1.00
| 0.00 | 1.00 | $900.00 | $900.00 |
| 51 | INSTALL 45' SIGNAL MAST ARM | 4.00 | EA |
3.00
| 0.00 | 3.00 | $900.00 | $2,700.00 |
| 52 | INSTALL 12' LUMINAIRE MAST ARM | 15.00 | EA |
13.00
| 0.00 | 13.00 | $900.00 | $11,700.00 |
| 53 | INSTALL 15' LUMINAIRE MAST ARM | 1.00 | EA |
1.00
| 0.00 | 1.00 | $900.00 | $900.00 |
| 54 | INSTALL 8' STRAIGHT ARM CLAMP-ON FOR STREET NAME SIGN | 8.00 | EA |
6.00
| 0.00 | 6.00 | $900.00 | $5,400.00 |
| 55 | 150 W EQ LED LUMINAIRE | 12.00 | EA |
12.00
| 0.00 | 12.00 | $1,200.00 | $14,400.00 |
| 56 | 200 W EQ LED LUMINAIRE | 4.00 | EA |
4.00
| 0.00 | 4.00 | $1,500.00 | $6,000.00 |
| 59 | LED COUNTDOWN PEDESTRIAN HEAD (COMPLETE) | 8.00 | EA |
7.00
| 0.00 | 7.00 | $1,300.00 | $9,100.00 |
| 60 | LED COUNTDOWN PEDESTRIAN HEAD (COMPLETE) | 8.00 | EA |
7.00
| 0.00 | 7.00 | $1,300.00 | $9,100.00 |
| 62 | 3-12" LED VEHICLE HEAD (COMPLETE) | 21.00 | EA |
17.00
| 0.00 | 17.00 | $1,300.00 | $22,100.00 |
| 63 | 5-12" LED VEHICLE HEAD (COMPLETE) | 16.00 | EA |
14.00
| 0.00 | 14.00 | $1,800.00 | $25,200.00 |
| 66 | 1" CONDUIT (SCH 80 PVC) | 100.00 | LF |
82.00
| 16.00 | 66.00 | $120.00 | $7,920.00 |
| 67 | 3" CONDUIT (SCH 80 PVC) | 750.00 | LF |
741.00
| 698.00 | 43.00 | $150.00 | $6,450.00 |
| 69 | 3-CONDUCTOR SIGNAL CABLE(EXCLUDING CONDUIT) | 2,200.00 | LF |
2,200.00
| 0.00 | 2,200.00 | $5.00 | $11,000.00 |
| 70 | 5-CONDUCTOR SIGNAL CABLE(EXCLUDING CONDUIT) | 670.00 | LF |
667.00
| 0.00 | 667.00 | $7.00 | $4,669.00 |
| 71 | 12-CONDUCTOR SIGNAL CABLE(EXCLUDING CONDUIT) | 2,200.00 | LF |
2,200.00
| 0.00 | 2,200.00 | $8.00 | $17,600.00 |
| 72 | #10 WIRE | 4,500.00 | LF |
2,132.00
| 0.00 | 2,132.00 | $3.00 | $6,396.00 |
| 95 | SCE WORK (ALLOWANCE OF $21,000) | 21,000.00 | AL |
9,157.49
| 0.00 | 9,157.49 | $1.00 | $9,157.49 |
| 98 | TRAFFIC CONTROL | 1.00 | LS |
0.50
| 0.25 | 0.25 | $80,000.00 | $20,000.00 |
| S-1 | CMS | | EA |
16.00
| 8.00 | 8.00 | $2,500.00 | $20,000.00 |
| S-3 | MILL AND FILL ON PARKER ROAD | | LS |
1.00
| 0.00 | 1.00 | $100,251.30 | $100,251.30 |
| S-5 | WEEKEND WORK RELATED TO S-3 | | LS |
1.00
| 0.00 | 1.00 | $7,777.00 | $7,777.00 |
| S-6 | ASPHALT CONCRETE PAVING | | LS |
1.00
| 0.00 | 1.00 | $9,566.00 | $9,566.00 |
| S-7 | WEEKEND WORK - RELATED TO S-6 | | LS |
1.00
| 0.00 | 1.00 | $7,777.00 | $7,777.00 |
|