| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 6.00 | MTH |
2.00
| 1.00 | 1.00 | $500.00 | $500.00 |
| 4 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
0.29
| 0.14 | 0.15 | $35,000.00 | $5,250.00 |
| 5 | IMPLEMENTATION OF BMPS | 1.00 | LS |
0.29
| 0.14 | 0.15 | $35,000.00 | $5,250.00 |
| 8 | IMPLEMENTATION OF THE SITE-SPECIFIC HEALTH AND SAFETY PLAN | 1.00 | LS |
0.29
| 0.14 | 0.15 | $35,000.00 | $5,250.00 |
| 12 | OFFICE FACILITIES | 7.00 | MTH |
2.00
| 1.00 | 1.00 | $5,000.00 | $5,000.00 |
| 13 | MOBILIZATION | 1.00 | LS |
0.75
| 0.50 | 0.25 | $200,000.00 | $50,000.00 |
| 14 | CLEARING AND GRUBBING | 1.00 | LS |
0.70
| 0.14 | 0.56 | $150,000.00 | $84,000.00 |
| 26 | 0.5 MG WATER STORAGE TANK AND APPURTENANCES | 1.00 | LS |
0.30
| 0.096 | 0.204 | $2,400,000.00 | $489,600.00 |
| 39 | TRAFFIC CONTROL | 1.00 | LS |
0.20
| 0.10 | 0.10 | $25,000.00 | $2,500.00 |