| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 6.00 | MTH |
3.00
| 2.00 | 1.00 | $500.00 | $500.00 |
| 4 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
0.43
| 0.29 | 0.14 | $35,000.00 | $4,900.00 |
| 5 | IMPLEMENTATION OF BMPS | 1.00 | LS |
0.43
| 0.29 | 0.14 | $35,000.00 | $4,900.00 |
| 8 | IMPLEMENTATION OF THE SITE-SPECIFIC HEALTH AND SAFETY PLAN | 1.00 | LS |
0.43
| 0.29 | 0.14 | $35,000.00 | $4,900.00 |
| 12 | OFFICE FACILITIES | 7.00 | MTH |
3.00
| 2.00 | 1.00 | $5,000.00 | $5,000.00 |
| 14 | CLEARING AND GRUBBING | 1.00 | LS |
0.95
| 0.70 | 0.25 | $150,000.00 | $37,500.00 |
| 23 | INITIAL VIDEO INSPECTION | 1.00 | LS |
1.00
| 0.00 | 1.00 | $2,500.00 | $2,500.00 |
| 26 | 0.5 MG WATER STORAGE TANK AND APPURTENANCES | 1.00 | LS |
0.69
| 0.30 | 0.39 | $2,400,000.00 | $936,000.00 |
| 27 | OVERFLOW PRECAST DROP INLET, 36" X 36" | 1.00 | EA |
0.90
| 0.00 | 0.90 | $10,000.00 | $9,000.00 |
| 28 | CLEANOUT DOOR PRECAST DROP INLET, 48" X 48" | 1.00 | EA |
0.90
| 0.00 | 0.90 | $10,000.00 | $9,000.00 |
| 30 | CONCRETE PAD (SURGE TANKS) | 17.00 | CY |
0.25
| 0.00 | 0.25 | $2,000.00 | $500.00 |
| 39 | TRAFFIC CONTROL | 1.00 | LS |
0.30
| 0.20 | 0.10 | $25,000.00 | $2,500.00 |
| S-2 | OVER-EX | | LS |
0.75
| 0.00 | 0.75 | $8,564.00 | $6,423.00 |
| S-4A | DEWATERING | | LS |
1.00
| 0.00 | 1.00 | $7,500.00 | $7,500.00 |