| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 13 | NOISE CONTROL (ALLOWANCE OF $70,000) | 70,000.00 | AL |
178,540.00
| 140,000.00 | 38,540.00 | $1.00 | $38,540.00 |
| 14 | NPDES MONITORING AND REPORTING | 9.00 | MTH |
6.00
| 0.00 | 6.00 | $10,656.00 | $63,936.00 |
| 23 | CONST & REMOVE TEMP CHAIN LINK FENCE | 1,298.00 | LF |
1,298.00
| 974.00 | 324.00 | $10.00 | $3,240.00 |
| 30 | SYSTEM INTEGRATION | 1.00 | LS |
0.75
| 0.00 | 0.75 | $80,285.00 | $60,213.75 |
| 31 | ELECTRICAL WORK | 1.00 | LS |
0.75
| 0.51 | 0.24 | $181,019.00 | $43,444.56 |
| S-3 | UNFORESEEN SOIL CONDITION DELAY COSTS | | LS |
1.00
| 0.00 | 1.00 | $135,000.00 | $135,000.00 |
| S-4 | UPGRADE EXISTING UG CONDUIT TO 2.5" | | LS |
1.00
| 0.00 | 1.00 | $74,000.00 | $74,000.00 |