Los Angeles County Public Works
Project Management Division III
Progress Payment 1
Project Name: Rosemead Boulevard Interim Complete Streets
Contractor: Los Angeles Engineering, Inc.
633 North Barranca Avenue
Covina, CA 91723
Project ID: RDC0016284
Federal Number(s): None
Original Contract: $2,699,500.00
Awarded: 3/13/2023
Period Ending: 7/31/2023
Board Accepted: 6/5/2024
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
1CONSTRUCTION SCHEDULE (BASELINE) (STIPULATED UNIT PRICE OF $2,500)1.00LS 1.00 0.001.00$2,500.00$2,500.00
2CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH)3.00MTH 0.33 0.000.33$1,500.00$495.00
4IMPLEMENTATION OF THE LTWHP1.00LS 1.00 0.001.00$15,000.00$15,000.00
5PREPARATION OF THE SWPPP (STIPULATED UNIT PRICE OF $5,000)1.00LS 1.00 0.001.00$5,000.00$5,000.00
6IMPLEMENTATION OF THE SWPPP1.00LS 0.33 0.000.33$25,000.00$8,250.00
7PREPARATION OF THE DIVERSION OF WATER PLAN (STIPULATED UNIT PRICE OF $5,000)1.00LS 1.00 0.001.00$5,000.00$5,000.00
8IMPLEMENTATION OF THE DIVERSION OF WATER PLAN1.00LS 0.50 0.000.50$75,000.00$37,500.00
9SHORING OF OPEN EXCAVATIONS1.00LS 0.50 0.000.50$284,711.00$142,355.50
11MOBILIZATION1.00LS 0.95 0.000.95$270,000.00$256,500.00
12CLEARING AND GRUBBING1.00LS 1.00 0.001.00$74,500.00$74,500.00
13TREE REMOVAL (13"-24" DIAMETER)1.00EA 1.00 0.001.00$4,000.00$4,000.00
14TREE REMOVAL (25"+ DIAMETER)1.00EA 1.00 0.001.00$8,000.00$8,000.00
15REMOVE EXISTING CHAIN LINK FENCE1,730.00LF 1,450.00 0.001,450.00$15.00$21,750.00
16REMOVE AND DISPOSE CHAIN LINK GATE2.00EA 2.00 0.002.00$900.00$1,800.00
17CONCRETE REMOVAL (NON-REINFORCED)96.00CY 96.00 0.0096.00$125.00$12,000.00
20REMOVE 18 " CSP58.00LF 58.00 0.0058.00$50.00$2,900.00
21UNCLASSIFIED EXCAVATION1,881.00CY 789.00 0.00789.00$160.00$126,240.00
22STRUCTURE EXCAVATION (RETAINING WALL)1,706.00CY 1,652.40 0.001,652.40$85.00$140,454.00
32REINFORCED CONCRETE RETAINING WALL TYPE 6 - CALTRANS294.00CY 35.50 0.0035.50$1,450.00$51,475.00
44TRANSPORTATION AND DISPOSAL OF TREATED WOOD WASTE9,370.00LB 9,140.00 0.009,140.00$1.00$9,140.00
4518" RCP, 2500 D65.00LF 65.00 0.0065.00$300.00$19,500.00
66TRAFFIC CONTROL1.00LS 0.50 0.000.50$75,000.00$37,500.00

DEDUCTION DETAIL

There are NO deductions this period

FINANCIAL SUMMARY

  Total Previous Current
Earned $981,859.50 $0.00 $981,859.50
Retained* $0.00 $0.00 $0.00
Deducted $0.00 $0.00 $0.00
Due $981,859.50 $0.00 $981,859.50



*This project has an escrow account.

Contact Office Engineer
Contractor Copy  
P Please consider the environment before printing this report.