| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 1 | CONSTRUCTION SCHEDULE (BASELINE) (STIPULATED UNIT PRICE OF $2,500) | 1.00 | LS |
1.00
| 0.00 | 1.00 | $2,500.00 | $2,500.00 |
| 4 | PREPARATION OF THE SWPPP (STIPULATED UNIT PRICE OF $2,500) | 1.00 | LS |
1.00
| 0.00 | 1.00 | $2,500.00 | $2,500.00 |
| 5 | IMPLEMENTATION OF THE SWPPP | 1.00 | LS |
0.25
| 0.00 | 0.25 | $20,815.80 | $5,203.95 |
| 6 | OFFICE FACILITIES | 4.00 | MTH |
1.00
| 0.00 | 1.00 | $7,434.22 | $7,434.22 |
| 7 | MOBILIZATION | 1.00 | LS |
0.50
| 0.00 | 0.50 | $81,776.37 | $40,888.19 |
| 8 | CLEARING AND GRUBBING | 1.00 | LS |
0.25
| 0.00 | 0.25 | $20,000.00 | $5,000.00 |
| 16 | CONCRETE REMOVAL (NON-REINFORCED) | 282.00 | CY |
59.00
| 0.00 | 59.00 | $371.71 | $21,930.89 |
| 18 | UNCLASSIFIED EXCAVATION | 1,840.00 | CY |
300.00
| 0.00 | 300.00 | $133.82 | $40,146.00 |
| 19 | CRUSHED MISCELLANEOUS BASE | 1,247.00 | CY |
162.00
| 0.00 | 162.00 | $66.91 | $10,839.42 |
| 25 | PCC CURB, TYPE A1-VAR | 132.00 | LF |
50.00
| 0.00 | 50.00 | $59.47 | $2,973.50 |
| 29 | PCC CURB & GUTTER, TYPE A2-VAR, W=1' | 535.00 | LF |
106.00
| 0.00 | 106.00 | $81.78 | $8,668.68 |
| 30 | PCC WALK, 4" THICK | 10,545.00 | SF |
747.00
| 0.00 | 747.00 | $13.38 | $9,994.86 |
| 32 | PCC CURB RAMPS | 73.00 | CY |
17.00
| 0.00 | 17.00 | $1,338.16 | $22,748.72 |
| 33 | PCC DRIVEWAYS, 6" THICK | 504.00 | SF |
270.00
| 0.00 | 270.00 | $17.84 | $4,816.80 |
| 34 | DETECTABLE WARNING SURFACE | 465.00 | SF |
90.00
| 0.00 | 90.00 | $74.34 | $6,690.60 |
| 84 | TRAFFIC CONTROL | 1.00 | LS |
0.25
| 0.00 | 0.25 | $53,526.35 | $13,381.59 |
| 85 | FLASHING ARROW SIGN | 2.00 | EA |
0.50
| 0.00 | 0.50 | $5,203.95 | $2,601.98 |
| 86 | CHANGEABLE MESSAGE SIGN | 2.00 | EA |
0.50
| 0.00 | 0.50 | $5,203.95 | $2,601.98 |
| S-1 | EXTENSION OF TIME, PART 1 NTP | | DAY |
28.00
| 0.00 | 28.00 | $0.00 | $0.00 |
|