| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 3.00 | MTH |
2.00
| 0.33 | 1.67 | $1,500.00 | $2,505.00 |
| 6 | IMPLEMENTATION OF THE SWPPP | 1.00 | LS |
0.66
| 0.33 | 0.33 | $25,000.00 | $8,250.00 |
| 8 | IMPLEMENTATION OF THE DIVERSION OF WATER PLAN | 1.00 | LS |
1.00
| 0.50 | 0.50 | $75,000.00 | $37,500.00 |
| 9 | SHORING OF OPEN EXCAVATIONS | 1.00 | LS |
0.75
| 0.50 | 0.25 | $284,711.00 | $71,177.75 |
| 10 | OFFICE FACILITIES | 4.00 | MTH |
1.00
| 0.00 | 1.00 | $3,000.00 | $3,000.00 |
| 11 | MOBILIZATION | 1.00 | LS |
1.00
| 0.95 | 0.05 | $270,000.00 | $13,500.00 |
| 18 | CONCRETE REMOVAL (REINFORCED) | 1.00 | CY |
1.00
| 0.00 | 1.00 | $1,500.00 | $1,500.00 |
| 21 | UNCLASSIFIED EXCAVATION | 1,881.00 | CY |
933.00
| 789.00 | 144.00 | $160.00 | $23,040.00 |
| 22 | STRUCTURE EXCAVATION (RETAINING WALL) | 1,706.00 | CY |
1,706.00
| 1,652.40 | 53.60 | $85.00 | $4,556.00 |
| 23 | STRUCTURE BACKFILL (RETAINING WALL) | 1,457.00 | CY |
730.00
| 0.00 | 730.00 | $75.00 | $54,750.00 |
| 32 | REINFORCED CONCRETE RETAINING WALL TYPE 6 - CALTRANS | 294.00 | CY |
265.12
| 35.50 | 229.62 | $1,450.00 | $332,949.00 |
| 34 | PCC CURB, TYPE A1-8 | 3,076.00 | LF |
866.00
| 0.00 | 866.00 | $25.00 | $21,650.00 |
| 35 | PCC CURB, TYPE A1-MOD | 2,247.00 | LF |
816.00
| 0.00 | 816.00 | $17.00 | $13,872.00 |
| 46 | FILTRATION TRENCH | 1,856.00 | LF |
612.00
| 0.00 | 612.00 | $78.00 | $47,736.00 |
| 66 | TRAFFIC CONTROL | 1.00 | LS |
0.75
| 0.50 | 0.25 | $75,000.00 | $18,750.00 |
| S-2 | ADD ADDITIONAL REBARS | | LS |
1.00
| 0.00 | 1.00 | $4,000.00 | $4,000.00 |
|