| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 5.00 | MTH |
3.00
| 2.00 | 1.00 | $500.00 | $500.00 |
| 4 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
0.60
| 0.40 | 0.20 | $35,000.00 | $7,000.00 |
| 5 | IMPLEMENTATION OF BMPS | 1.00 | LS |
0.60
| 0.40 | 0.20 | $35,000.00 | $7,000.00 |
| 7 | IMPLEMENTATION OF THE SITE-SPECIFIC HEALTH AND SAFETY PLAN | 1.00 | LS |
0.60
| 0.40 | 0.20 | $35,000.00 | $7,000.00 |
| 9 | IMPLEMENTATION OF THE SURFACE WATER DIVERSION PLAN | 1.00 | LS |
0.50
| 0.25 | 0.25 | $150,000.00 | $37,500.00 |
| 11 | IMPLEMENTATION OF THE COFFERDAM DEWATERING PLAN | 1.00 | LS |
0.50
| 0.25 | 0.25 | $250,000.00 | $62,500.00 |
| 14 | MAINTENANCE OF WILDLIFE EXCLUSIONARY FENCING | 925.00 | LF |
690.00
| 460.00 | 230.00 | $20.00 | $4,600.00 |
| 15 | OFFICE FACILITIES | 6.00 | MTH |
3.00
| 2.00 | 1.00 | $3,500.00 | $3,500.00 |
| 16 | MOBILIZATION | 1.00 | LS |
1.00
| 0.95 | 0.05 | $432,750.00 | $21,637.50 |
| 17 | CONCRETE REMOVAL (REINFORCED) | 525.00 | CY |
505.00
| 504.20 | 0.80 | $1,000.00 | $800.00 |
| 18 | UNCLASSIFIED EXCAVATION | 9,200.00 | CY |
7,625.50
| 7,519.20 | 106.30 | $85.00 | $9,035.50 |
| 19 | CRUSHED MISCELLANEOUS BASE | 200.00 | CY |
74.00
| 0.00 | 74.00 | $120.00 | $8,880.00 |
| 24 | CONCRETE PILES, 45 TONS | 1,728.00 | LF |
563.40
| 428.00 | 135.40 | $250.00 | $33,850.00 |
| 26 | 11' - 0" W X 9' - 2" H RCB PER SECTION B1-B, SHEET 5 | 340.00 | CY |
322.00
| 0.00 | 322.00 | $3,300.00 | $1,062,600.00 |
| 27 | DEBRIS REMOVAL | 1.00 | LS |
0.50
| 0.00 | 0.50 | $50,000.00 | $25,000.00 |
| 35 | PRESTRESSED CONCRETE PILE DRIVING TEST | 4.00 | EACH |
4.00
| 0.00 | 4.00 | $5,000.00 | $20,000.00 |
| 40 | TRAFFIC CONTROL | 1.00 | LS |
0.60
| 0.40 | 0.20 | $50,000.00 | $10,000.00 |
| S-2A | PILE FREIGHT | | LS |
1.00
| 0.00 | 1.00 | $10,400.00 | $10,400.00 |
|