| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 3.00 | MTH |
2.00
| 1.00 | 1.00 | $500.00 | $500.00 |
| 5 | IMPLEMENTATION OF THE SWPPP | 1.00 | LS |
0.75
| 0.50 | 0.25 | $20,815.80 | $5,203.95 |
| 6 | OFFICE FACILITIES | 4.00 | MTH |
3.00
| 2.00 | 1.00 | $7,434.22 | $7,434.22 |
| 7 | MOBILIZATION | 1.00 | LS |
1.00
| 0.75 | 0.25 | $81,776.37 | $20,444.09 |
| 8 | CLEARING AND GRUBBING | 1.00 | LS |
1.00
| 0.50 | 0.50 | $20,000.00 | $10,000.00 |
| 10 | TREE REMOVAL (13"-24" DIAMETER) | 1.00 | EA |
8.00
| 0.00 | 8.00 | $3,717.11 | $29,736.88 |
| 12 | CROWN REDUCTION, TREE (13" - 24" DIAMETER) | 2.00 | EA |
2.00
| 0.00 | 2.00 | $1,263.82 | $2,527.64 |
| 15 | REMOVE EXISTING CHAIN LINK FENCE (INCL CONC CURB AND FOOTING) | 29.00 | LF |
29.00
| 0.00 | 29.00 | $148.68 | $4,311.72 |
| 16 | CONCRETE REMOVAL (NON-REINFORCED) | 282.00 | CY |
282.00
| 206.00 | 76.00 | $371.71 | $28,249.96 |
| 18 | UNCLASSIFIED EXCAVATION | 1,840.00 | CY |
1,840.00
| 877.00 | 963.00 | $133.82 | $128,868.66 |
| 19 | CRUSHED MISCELLANEOUS BASE | 1,247.00 | CY |
1,247.00
| 600.00 | 647.00 | $66.91 | $43,290.77 |
| 21 | AC PAVEMENT | 811.00 | TON |
811.00
| 254.00 | 557.00 | $178.42 | $99,379.94 |
| 23 | AC PAVEMENT(DRIVEWAYS) | 14.00 | TON |
13.00
| 0.00 | 13.00 | $297.37 | $3,865.81 |
| 24 | RECONSTRUCT MANHOLE | 5.00 | EA |
5.00
| 3.00 | 2.00 | $5,203.95 | $10,407.90 |
| 27 | PCC CURB & GUTTER, TYPE A2-8 | 112.00 | LF |
112.00
| 0.00 | 112.00 | $81.78 | $9,159.36 |
| 28 | PCC CURB & GUTTER, TYPE A2-VAR | 401.00 | LF |
401.00
| 213.00 | 188.00 | $81.78 | $15,374.64 |
| 29 | PCC CURB & GUTTER, TYPE A2-VAR, W=1' | 535.00 | LF |
535.00
| 334.00 | 201.00 | $81.78 | $16,437.78 |
| 30 | PCC WALK, 4" THICK | 10,545.00 | SF |
10,100.00
| 5,839.00 | 4,261.00 | $13.38 | $57,012.18 |
| 32 | PCC CURB RAMPS | 73.00 | CY |
73.00
| 44.00 | 29.00 | $1,338.16 | $38,806.64 |
| 33 | PCC DRIVEWAYS, 6" THICK | 504.00 | SF |
459.00
| 270.00 | 189.00 | $17.84 | $3,371.76 |
| 34 | DETECTABLE WARNING SURFACE | 465.00 | SF |
465.00
| 255.00 | 210.00 | $74.34 | $15,611.40 |
| 35 | CROSS GUTTER | 101.00 | CY |
101.00
| 73.00 | 28.00 | $1,115.13 | $31,223.64 |
| 37 | 1" CONDUIT (SCH 80 PVC) | 115.00 | LF |
81.00
| 0.00 | 81.00 | $104.08 | $8,430.48 |
| 38 | 1-1/2" CONDUIT (SCH 80 PVC) | 10.00 | LF |
10.00
| 0.00 | 10.00 | $111.51 | $1,115.10 |
| 39 | 3" CONDUIT (SCH 80 PVC) | 50.00 | LF |
30.00
| 0.00 | 30.00 | $126.38 | $3,791.40 |
| 44 | NO. 6 PULL BOX INCL PCC COVER | 6.00 | EA |
6.00
| 2.00 | 4.00 | $1,338.16 | $5,352.64 |
| 45 | COMPOSITE TYPE 3 PULL BOX INCL COVER | 10.00 | EA |
9.00
| 0.00 | 9.00 | $1,115.13 | $10,036.17 |
| 47 | REMOVE PULL BOX | 10.00 | EA |
9.00
| 0.00 | 9.00 | $743.42 | $6,690.78 |
| 48 | REMOVE PEDESTRIAN PUSH BUTTON POST | 1.00 | EA |
1.00
| 0.00 | 1.00 | $446.05 | $446.05 |
| 52 | REMOVE PEDESTRIAN PUSH BUTTON POST FOUNDATION | 1.00 | EA |
1.00
| 0.00 | 1.00 | $892.11 | $892.11 |
| 56 | PEDESTRIAN PUSH BUTTON POST FOUNDATION | 10.00 | EA |
9.00
| 0.00 | 9.00 | $1,189.47 | $10,705.23 |
| 74 | REMOVE STRIPING | 733.00 | LF |
200.00
| 0.00 | 200.00 | $2.75 | $550.00 |
| 75 | REMOVE PAVEMENT MARKINGS (THERMOPLASTIC) | 3,495.00 | SF |
500.00
| 0.00 | 500.00 | $3.12 | $1,560.00 |
| 78 | SIGN PANEL | 37.00 | EA |
37.00
| 0.00 | 37.00 | $223.03 | $8,252.11 |
| 79 | SIGN POST (ROADSIDE SIGN) | 21.00 | EA |
21.00
| 0.00 | 21.00 | $297.37 | $6,244.77 |
| 80 | RELOCATE SIGN | 14.00 | EA |
14.00
| 0.00 | 14.00 | $111.51 | $1,561.14 |
| 81 | RELOCATE SIGN POST | 7.00 | EA |
7.00
| 0.00 | 7.00 | $185.86 | $1,301.02 |
| 82 | REMOVE SIGN | 13.00 | EA |
13.00
| 0.00 | 13.00 | $74.34 | $966.42 |
| 83 | REMOVE SIGN POST | 6.00 | EA |
6.00
| 0.00 | 6.00 | $111.51 | $669.06 |
| 84 | TRAFFIC CONTROL | 1.00 | LS |
0.75
| 0.50 | 0.25 | $53,526.35 | $13,381.59 |
| 85 | FLASHING ARROW SIGN | 2.00 | EA |
1.50
| 1.00 | 0.50 | $5,203.95 | $2,601.98 |
| 86 | CHANGEABLE MESSAGE SIGN | 2.00 | EA |
1.50
| 1.00 | 0.50 | $5,203.95 | $2,601.98 |
| S-4 | PREMIUM OVERTIME WEEKEND PAVING | | LS |
1.00
| 0.33 | 0.67 | $30,000.00 | $20,100.00 |
|