Los Angeles County Public Works
Project Management Division III
Progress Payment 3
Project Name: Rosemead Boulevard Interim Complete Streets
Contractor: Los Angeles Engineering, Inc.
633 North Barranca Avenue
Covina, CA 91723
Project ID: RDC0016284
Federal Number(s): None
Original Contract: $2,699,500.00
Awarded: 3/13/2023
Period Ending: 10/20/2023
Board Accepted: 6/5/2024
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
2CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH)3.00MTH 3.00 2.001.00$1,500.00$1,500.00
6IMPLEMENTATION OF THE SWPPP1.00LS 1.00 0.660.34$25,000.00$8,500.00
9SHORING OF OPEN EXCAVATIONS1.00LS 1.00 0.750.25$284,711.00$71,177.75
10OFFICE FACILITIES4.00MTH 3.00 1.002.00$3,000.00$6,000.00
19REMOVE AND DISPOSE BOLLARD1.00EA 1.00 0.001.00$250.00$250.00
21UNCLASSIFIED EXCAVATION1,881.00CY 1,881.00 933.00948.00$160.00$151,680.00
23STRUCTURE BACKFILL (RETAINING WALL)1,457.00CY 1,457.00 730.00727.00$75.00$54,525.00
24CRUSHED MISCELLANEOUS BASE135.00CY 135.00 0.00135.00$160.00$21,600.00
25COLD MILL AC PAVEMENT (0 - 1-1/2")13,133.00SF 13,133.00 0.0013,133.00$2.00$26,266.00
31PCC PAVEMENT20.00CY 20.00 0.0020.00$650.00$13,000.00
32REINFORCED CONCRETE RETAINING WALL TYPE 6 - CALTRANS294.00CY 294.00 265.1228.88$1,450.00$41,876.00
34PCC CURB, TYPE A1-83,076.00LF 3,076.00 866.002,210.00$25.00$55,250.00
35PCC CURB, TYPE A1-MOD2,247.00LF 2,247.00 816.001,431.00$17.00$24,327.00
36PCC WALK, 4" THICK919.00SF 919.00 0.00919.00$9.00$8,271.00
37PCC CURB RAMPS7.00CY 7.00 0.007.00$2,200.00$15,400.00
38CASE CM CURB RAMP1.00EA 1.00 0.001.00$5,500.00$5,500.00
41CHAIN LINK FENCE, 5' HIGH1,284.00LF 1,006.00 0.001,006.00$50.00$50,300.00
42CHAIN LINK FENCE, 5' HIGH ON TOP OF WALL456.00LF 456.00 0.00456.00$50.00$22,800.00
43ROLLING CHAIN LINK GATE2.00EA 1.00 0.001.00$10,000.00$10,000.00
46FILTRATION TRENCH1,856.00LF 1,856.00 612.001,244.00$78.00$97,032.00
66TRAFFIC CONTROL1.00LS 0.90 0.750.15$75,000.00$11,250.00

DEDUCTION DETAIL

There are NO deductions this period

FINANCIAL SUMMARY

  Total Previous Current
Earned $2,337,100.00 $1,640,595.25 $696,504.75
Retained* $67,762.02 $32,936.78 $34,825.24
Deducted $0.00 $0.00 $0.00
Due $2,269,337.98 $1,607,658.47 $661,679.51