| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 5.00 | MTH |
4.00
| 3.00 | 1.00 | $500.00 | $500.00 |
| 4 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
0.80
| 0.60 | 0.20 | $35,000.00 | $7,000.00 |
| 5 | IMPLEMENTATION OF BMPS | 1.00 | LS |
0.80
| 0.60 | 0.20 | $35,000.00 | $7,000.00 |
| 7 | IMPLEMENTATION OF THE SITE-SPECIFIC HEALTH AND SAFETY PLAN | 1.00 | LS |
0.80
| 0.60 | 0.20 | $35,000.00 | $7,000.00 |
| 9 | IMPLEMENTATION OF THE SURFACE WATER DIVERSION PLAN | 1.00 | LS |
0.75
| 0.50 | 0.25 | $150,000.00 | $37,500.00 |
| 11 | IMPLEMENTATION OF THE COFFERDAM DEWATERING PLAN | 1.00 | LS |
0.75
| 0.50 | 0.25 | $250,000.00 | $62,500.00 |
| 14 | MAINTENANCE OF WILDLIFE EXCLUSIONARY FENCING | 925.00 | LF |
920.00
| 690.00 | 230.00 | $20.00 | $4,600.00 |
| 15 | OFFICE FACILITIES | 6.00 | MTH |
4.00
| 3.00 | 1.00 | $3,500.00 | $3,500.00 |
| 18 | UNCLASSIFIED EXCAVATION | 9,200.00 | CY |
8,294.00
| 7,625.50 | 668.50 | $85.00 | $56,822.50 |
| 19 | CRUSHED MISCELLANEOUS BASE | 200.00 | CY |
118.00
| 74.00 | 44.00 | $120.00 | $5,280.00 |
| 20 | REMOVE EXISTING FENCE | 483.00 | LF |
483.00
| 0.00 | 483.00 | $20.00 | $9,660.00 |
| 24 | CONCRETE PILES, 45 TONS | 1,728.00 | LF |
1,800.00
| 563.40 | 1,236.60 | $250.00 | $309,150.00 |
| 25 | 11' - 0" W X 9' - 2" H RCB PER SECTION B1-A, SHEET 4 | 292.00 | CY |
208.00
| 0.00 | 208.00 | $3,600.00 | $748,800.00 |
| 34 | MARKER LIGHTS | 1.00 | LS |
1.00
| 0.00 | 1.00 | $25,000.00 | $25,000.00 |
| 40 | TRAFFIC CONTROL | 1.00 | LS |
0.80
| 0.60 | 0.20 | $50,000.00 | $10,000.00 |
|