Los Angeles County Public Works
Project Management Division III
Progress Payment 27
Project Name: Pacoima Spreading Grounds Basin Enhancement Project
Contractor: AMES CONSTRUCTION INC
2500 County Road 42 West
Burnsville , MN 55337
Project ID: FCC0001207
Federal Number(s): None
Original Contract: $54,483,460.00
Awarded: 5/6/2021
Period Ending: 10/20/2023
Board Accepted: 6/10/2025
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
2CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH)34.00MTH 25.00 24.001.00$500.00$500.00
4IMPLEMENTATION OF THE LTWHP1.00LS 0.75 0.720.03$115,000.00$3,450.00
6IMPLEMENTATION OF THE SWPPP1.00LS 0.75 0.720.03$300,000.00$9,000.00
12IMPLEMENTATION OF THE FUGITIVE DUST CONTROL PLAN34.00MTH 25.00 24.001.00$8,000.00$8,000.00
15VEHICLES AND EQUIPMENT EMISSIONS REPORTING34.00MTH 25.00 24.001.00$8,000.00$8,000.00
18NOISE MONITORING AND REPORTING34.00MTH 25.00 24.001.00$6,000.00$6,000.00
20IMPLEMENTATION OF THE QUALITY CONTROL PROGRAM FOR MOISTURE CONTENT682.00DAY 451.00 429.0022.00$1,000.00$22,000.00
22OFFICE FACILITIES34.00MTH 25.00 24.001.00$5,000.00$5,000.00
25MAINTENANCE OF TIRE WASHES90.00MTH 58.00 55.003.00$3,500.00$10,500.00
26WATER TRUCKS682.00DAY 487.00 464.0023.00$1,500.00$34,500.00
27STREET SWEEPING682.00DAYS 475.00 453.0022.00$1,500.00$33,000.00
30MAINTENANCE OF TEMPORARY SOUND BARRIER5,800.00LF 4,275.00 4,104.00171.00$23.00$3,933.00
44UNCLASSIFIED EXCAVATION13,881.00CY 12,515.40 11,149.801,365.60$9.00$12,290.40
45BASIN EXCAVATION2,085,952.00CY 1,164,614.00 1,144,791.0019,823.00$2.30$45,592.90
49EXCAVATION, TRANSPORTATION AND DISPOSAL OF EXCESS BASIN MATERIAL1,343,403.00CY 1,139,888.32 1,087,043.7352,844.59$15.00$792,668.85
50EXCAVATION, TRANSPORTATION AND DISPOSAL OF DELINEATED SOIL31,268.00CY 11,452.30 6,712.634,739.67$21.00$99,533.07
72AC PAVEMENT (TEMPORARY ACCESS ROAD MAINTENANCE)1,500.00TON 1,215.00 1,080.00135.00$25.00$3,375.00
137ELECTRICAL WORK1.00LS 0.85 0.750.10$920,000.00$92,000.00
138TRAFFIC CONTROL1.00LS 0.69 0.660.03$100,000.00$3,000.00
144PLANT ESTABLISHMENT PERIOD1.00LS 0.25 0.000.25$18,000.00$4,500.00

DEDUCTION DETAIL

There are NO deductions this period

FINANCIAL SUMMARY

  Total Previous Current
Earned $44,046,532.59 $42,849,689.37 $1,196,843.22
Retained $2,202,326.65 $2,142,484.49 $59,842.16
Deducted $0.00 $0.00 $0.00
Due $41,844,205.94 $40,707,204.88 $1,137,001.06



Contact Office Engineer
Contractor Copy  