Los Angeles County Public Works
Project Management Division III
Progress Payment 5
Project Name: Los Nietos Safe Routes to School - Phase 2
Contractor: Access Pacific, Inc.
2835 Sierra Grande Street
Pasadena, CA 91107
Project ID: RDC0016316
Federal Number(s): ATPL-5953(763)
Original Contract: $1,684,238.15
Awarded: 2/28/2023
Period Ending: 12/6/2023
Board Accepted: 3/11/2025
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
33PCC DRIVEWAYS, 6" THICK504.00SF 486.00 459.0027.00$17.84$481.68
402-PAIR DETECTOR LEAD-IN CABLE80.00LF 80.00 0.0080.00$14.87$1,189.60
413-CONDUCTOR SIGNAL CABLE(EXCLUDING CONDUIT)1,559.00LF 1,459.00 1,000.00459.00$10.41$4,778.19
46INDUCTIVE LOOP DETECTOR AND LEADS SAW CUT2,131.00LF 2,010.00 0.002,010.00$20.82$41,848.20
62APS PPB WITH SPECIAL VOICE MESSAGE1.00EA 1.00 0.001.00$11,300.01$11,300.01
65REWIRE CONTROLLER CABINET1.00EA 1.00 0.001.00$7,136.85$7,136.85
69DETAIL 39A (THERMOPLASTIC)240.00LF 240.00 0.00240.00$2.23$535.20
7112" STRIPING (THERMOPLASTIC)595.00LF 595.00 459.00136.00$5.20$707.20
73PAVEMENT MARKINGS (THERMOPLASTIC)549.00SF 549.00 480.0069.00$8.55$589.95
75REMOVE PAVEMENT MARKINGS (THERMOPLASTIC)3,495.00SF 2,784.00 1,524.001,260.00$3.12$3,931.20
S-5CONDUIT CROSSING EA 1.00 0.001.00$31,500.00$31,500.00

DEDUCTION DETAIL

DescriptionUnitTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
EXHIBIT 16-ZLUMP SUM 4.00 3.001.00$1,000.00 $1,000.00
EXHIBIT 9-FLUMP SUM 3.00 2.001.00$1,000.00 $1,000.00

FINANCIAL SUMMARY

  Total Previous Current
Earned $1,763,259.99 $1,659,261.91 $103,998.08
Retained $88,163.00 $82,963.10 $5,199.90
Deducted $7,000.00 $5,000.00 $2,000.00
Due $1,668,096.99 $1,571,298.81 $96,798.18



Contact Office Engineer
Contractor Copy  
P Please consider the environment before printing this report.