Los Angeles County Public Works
Project Management Division III
Progress Payment 4
Project Name: Rosemead Boulevard Interim Complete Streets
Contractor: Los Angeles Engineering, Inc.
633 North Barranca Avenue
Covina, CA 91723
Project ID: RDC0016284
Federal Number(s): None
Original Contract: $2,699,500.00
Awarded: 3/13/2023
Period Ending: 11/30/2023
Board Accepted: 6/5/2024
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
3CONSTRUCTION SCHEDULE (AS-BUILT) (STIPULATED UNIT PRICE OF $1,000)1.00LS 1.00 0.001.00$1,000.00$1,000.00
10OFFICE FACILITIES4.00MTH 4.00 3.001.00$3,000.00$3,000.00
14TREE REMOVAL (25"+ DIAMETER)1.00EA 2.00 1.001.00$8,000.00$8,000.00
17CONCRETE REMOVAL (NON-REINFORCED)96.00CY 142.00 96.0046.00$125.00$5,750.00
26AC CURB, TYPE D1-858.00LF 58.00 0.0058.00$60.00$3,480.00
27AC CURB, TYPE D1-VAR28.00LF 28.00 0.0028.00$60.00$1,680.00
28AC PAVEMENT1,175.00TON 1,175.00 0.001,175.00$150.00$176,250.00
29AC PAVEMENT(PATCH BACK)69.00TON 69.00 0.0069.00$350.00$24,150.00
30AC PAVEMENT(DRIVEWAYS)24.00TON 24.00 0.0024.00$400.00$9,600.00
32REINFORCED CONCRETE RETAINING WALL TYPE 6 - CALTRANS294.00CY 296.00 294.002.00$1,450.00$2,900.00
33PCC CURB, TYPE A1-635.00LF 35.00 0.0035.00$130.00$4,550.00
39DETECTABLE WARNING SURFACE140.00SF 140.00 0.00140.00$40.00$5,600.00
40METAL HAND RAILINGS PER STD PLAN 606169.00LF 169.00 0.00169.00$175.00$29,575.00
41CHAIN LINK FENCE, 5' HIGH1,284.00LF 1,284.00 1,006.00278.00$50.00$13,900.00
43ROLLING CHAIN LINK GATE2.00EA 2.00 1.001.00$10,000.00$10,000.00
44TRANSPORTATION AND DISPOSAL OF TREATED WOOD WASTE9,370.00LB 9,370.00 9,140.00230.00$1.00$230.00
46FILTRATION TRENCH1,856.00LF 2,247.00 1,856.00391.00$78.00$30,498.00
47INDUCTIVE LOOP DETECTOR AND LEADS SAW CUT1,239.00LF 1,239.00 0.001,239.00$15.00$18,585.00
48DETAIL 1 (MODIFIED) (THERMOPLASTIC)3,180.00LF 3,180.00 0.003,180.00$1.00$3,180.00
49DETAIL 9 (THERMOPLASTIC)880.00LF 496.00 0.00496.00$0.80$396.80
50DETAIL 27 (THERMOPLASTIC)645.00LF 645.00 0.00645.00$1.50$967.50
51DETAIL 27B (THERMOPLASTIC)7,100.00LF 7,100.00 0.007,100.00$1.00$7,100.00
52DETAIL 38 (THERMOPLASTIC)350.00LF 350.00 0.00350.00$1.30$455.00
53PAVEMENT MARKINGS (THERMOPLASTIC)177.00SF 45.00 0.0045.00$9.00$405.00
558" STRIPING (THERMOPLASTIC)635.00LF 622.00 0.00622.00$1.20$746.40
5612" STRIPING (THERMOPLASTIC)200.00LF 192.00 0.00192.00$4.00$768.00
5724" STRIPING (THERMOPLASTIC)1,320.00LF 1,188.00 0.001,188.00$8.00$9,504.00
58CURB MARKINGS (ONE-COAT PAINT)130.00LF 130.00 0.00130.00$4.50$585.00
59REMOVE PAVEMENT MARKINGS (THERMOPLASTIC)45.00SF 45.00 0.0045.00$2.20$99.00
60REMOVE STRIPING (THERMOPLASTIC)4,401.00LF 2,156.00 0.002,156.00$1.50$3,234.00
61SIGN PANEL23.00EA 23.00 0.0023.00$120.00$2,760.00
62RELOCATE SIGN10.00EA 9.00 0.009.00$100.00$900.00
63REMOVE SIGN4.00EA 2.00 0.002.00$60.00$120.00
64RELOCATE SIGN POST9.00EA 9.00 0.009.00$220.00$1,980.00
65SIGN POST (ROADSIDE SIGN)9.00EA 9.00 0.009.00$350.00$3,150.00
66TRAFFIC CONTROL1.00LS 1.00 0.900.10$75,000.00$7,500.00

DEDUCTION DETAIL

There are NO deductions this period

FINANCIAL SUMMARY

  Total Previous Current
Earned $2,729,698.70 $2,337,100.00 $392,598.70
Retained* $87,391.96 $67,762.02 $19,629.94
Deducted $0.00 $0.00 $0.00
Due $2,642,306.74 $2,269,337.98 $372,968.76