| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 34.00 | MTH |
26.00
| 25.00 | 1.00 | $500.00 | $500.00 |
| 4 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
0.78
| 0.75 | 0.03 | $115,000.00 | $3,450.00 |
| 6 | IMPLEMENTATION OF THE SWPPP | 1.00 | LS |
0.78
| 0.75 | 0.03 | $300,000.00 | $9,000.00 |
| 12 | IMPLEMENTATION OF THE FUGITIVE DUST CONTROL PLAN | 34.00 | MTH |
26.00
| 25.00 | 1.00 | $8,000.00 | $8,000.00 |
| 15 | VEHICLES AND EQUIPMENT EMISSIONS REPORTING | 34.00 | MTH |
26.00
| 25.00 | 1.00 | $8,000.00 | $8,000.00 |
| 18 | NOISE MONITORING AND REPORTING | 34.00 | MTH |
26.00
| 25.00 | 1.00 | $6,000.00 | $6,000.00 |
| 20 | IMPLEMENTATION OF THE QUALITY CONTROL PROGRAM FOR MOISTURE CONTENT | 682.00 | DAY |
471.00
| 451.00 | 20.00 | $1,000.00 | $20,000.00 |
| 22 | OFFICE FACILITIES | 34.00 | MTH |
26.00
| 25.00 | 1.00 | $5,000.00 | $5,000.00 |
| 25 | MAINTENANCE OF TIRE WASHES | 90.00 | MTH |
61.00
| 58.00 | 3.00 | $3,500.00 | $10,500.00 |
| 26 | WATER TRUCKS | 682.00 | DAY |
507.00
| 487.00 | 20.00 | $1,500.00 | $30,000.00 |
| 27 | STREET SWEEPING | 682.00 | DAYS |
495.00
| 475.00 | 20.00 | $1,500.00 | $30,000.00 |
| 28 | PORTABLE SCALES | 3.00 | EA |
3.00
| 2.00 | 1.00 | $180,000.00 | $180,000.00 |
| 30 | MAINTENANCE OF TEMPORARY SOUND BARRIER | 5,800.00 | LF |
4,446.00
| 4,275.00 | 171.00 | $23.00 | $3,933.00 |
| 41 | REMOVE EXISTING CHAIN LINK FENCE | 11,950.00 | LF |
5,332.00
| 4,332.00 | 1,000.00 | $7.50 | $7,500.00 |
| 45 | BASIN EXCAVATION | 2,085,952.00 | CY |
1,172,176.00
| 1,164,614.00 | 7,562.00 | $2.30 | $17,392.60 |
| 49 | EXCAVATION, TRANSPORTATION AND DISPOSAL OF EXCESS BASIN MATERIAL | 1,343,403.00 | CY |
1,184,463.55
| 1,139,888.32 | 44,575.23 | $15.00 | $668,628.45 |
| 50 | EXCAVATION, TRANSPORTATION AND DISPOSAL OF DELINEATED SOIL | 31,268.00 | CY |
14,373.78
| 11,452.30 | 2,921.48 | $21.00 | $61,351.08 |
| 70 | AC PAVEMENT | 13,973.00 | TON |
12,223.34
| 7,435.66 | 4,787.68 | $100.00 | $478,768.00 |
| 75 | GAUGE BOARD | 16.00 | EA |
2.00
| 0.00 | 2.00 | $4,500.00 | $9,000.00 |
| 83 | REINFORCED CONCRETE OVERFLOW STRUCTURE EAST SETTLING BASIN | 1.00 | LS |
0.95
| 0.90 | 0.05 | $246,000.00 | $12,300.00 |
| 84 | REINFORCED CONCRETE OVERFLOW STRUCTURE WEST SETTLING BASIN | 1.00 | LS |
0.95
| 0.90 | 0.05 | $280,000.00 | $14,000.00 |
| 85 | REINFORCED CONCRETE OVERFLOW STRUCTURE NO. 1 | 1.00 | LS |
0.95
| 0.90 | 0.05 | $295,000.00 | $14,750.00 |
| 86 | REINFORCED CONCRETE OVERFLOW STRUCTURE NO. 2 | 1.00 | LS |
0.95
| 0.90 | 0.05 | $260,000.00 | $13,000.00 |
| 87 | REINFORCED CONCRETE OVERFLOW STRUCTURE NO. 3 | 1.00 | LS |
0.95
| 0.90 | 0.05 | $293,000.00 | $14,650.00 |
| 89 | REINFORCED CONCRETE OVERFLOW STRUCTURE NO. 5 | 1.00 | LS |
0.95
| 0.90 | 0.05 | $270,000.00 | $13,500.00 |
| 90 | REINFORCED CONCRETE OVERFLOW STRUCTURE NO. 6 | 1.00 | LS |
0.95
| 0.90 | 0.05 | $285,000.00 | $14,250.00 |
| 137 | ELECTRICAL WORK | 1.00 | LS |
0.90
| 0.85 | 0.05 | $920,000.00 | $46,000.00 |
| 138 | TRAFFIC CONTROL | 1.00 | LS |
0.72
| 0.69 | 0.03 | $100,000.00 | $3,000.00 |
| 144 | PLANT ESTABLISHMENT PERIOD | 1.00 | LS |
0.50
| 0.25 | 0.25 | $18,000.00 | $4,500.00 |
| S-15 | FENCE MODIFICATION WORK | | LS |
0.04
| 0.00 | 0.04 | $877,927.00 | $35,117.08 |
|