| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 5.00 | MTH |
5.00
| 4.00 | 1.00 | $500.00 | $500.00 |
| 4 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
0.90
| 0.80 | 0.10 | $35,000.00 | $3,500.00 |
| 5 | IMPLEMENTATION OF BMPS | 1.00 | LS |
0.90
| 0.80 | 0.10 | $35,000.00 | $3,500.00 |
| 7 | IMPLEMENTATION OF THE SITE-SPECIFIC HEALTH AND SAFETY PLAN | 1.00 | LS |
0.90
| 0.80 | 0.10 | $35,000.00 | $3,500.00 |
| 9 | IMPLEMENTATION OF THE SURFACE WATER DIVERSION PLAN | 1.00 | LS |
0.90
| 0.75 | 0.15 | $150,000.00 | $22,500.00 |
| 11 | IMPLEMENTATION OF THE COFFERDAM DEWATERING PLAN | 1.00 | LS |
0.90
| 0.75 | 0.15 | $250,000.00 | $37,500.00 |
| 14 | MAINTENANCE OF WILDLIFE EXCLUSIONARY FENCING | 925.00 | LF |
1,032.00
| 920.00 | 112.00 | $20.00 | $2,240.00 |
| 15 | OFFICE FACILITIES | 6.00 | MTH |
5.00
| 4.00 | 1.00 | $3,500.00 | $3,500.00 |
| 21 | TRANSITION STRUCTURE PER STD PLAN 341 | 1.00 | EA |
1.00
| 0.00 | 1.00 | $70,000.00 | $70,000.00 |
| 22 | PRESSURE MANHOLE PER STD PLAN 323 | 1.00 | EA |
1.00
| 0.00 | 1.00 | $25,000.00 | $25,000.00 |
| 25 | 11' - 0" W X 9' - 2" H RCB PER SECTION B1-A, SHEET 4 | 292.00 | CY |
298.00
| 208.00 | 90.00 | $3,600.00 | $324,000.00 |
| 27 | DEBRIS REMOVAL | 1.00 | LS |
0.75
| 0.50 | 0.25 | $50,000.00 | $12,500.00 |
| 32 | CONSTRUCT AND REMOVE SHEET PILE COFFERDAM, H=30' | 720.00 | LF |
627.00
| 504.00 | 123.00 | $1,350.00 | $166,050.00 |
| 33 | CONSTRUCT AND REMOVE SHEET PILE COFFERDAM, H=40' | 210.00 | LF |
157.00
| 147.00 | 10.00 | $1,800.00 | $18,000.00 |
| 36 | RESTORATION OF BEACH GROUND SURFACE | 1.00 | LS |
0.50
| 0.00 | 0.50 | $35,000.00 | $17,500.00 |
| 40 | TRAFFIC CONTROL | 1.00 | LS |
0.90
| 0.80 | 0.10 | $50,000.00 | $5,000.00 |
| S-3A | COFFERDAM WATER INTRUSION | | LS |
1.00
| 0.00 | 1.00 | $139,000.00 | $139,000.00 |
| S-4 | CONCRETE PILE EXPOSED REBAR COATING | | LS |
1.00
| 0.00 | 1.00 | $20,000.00 | $20,000.00 |