Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 8.00 | MTH |
5.00
| 4.00 | 1.00 | $500.00 | $500.00 |
5 | IMPLEMENTATION OF THE SWPPP | 1.00 | LS |
0.50
| 0.40 | 0.10 | $23,000.00 | $2,300.00 |
6 | OFFICE FACILITIES | 9.00 | MTH |
5.00
| 4.00 | 1.00 | $2,600.00 | $2,600.00 |
15 | CONCRETE REMOVAL (NON-REINFORCED) | 3,146.00 | CY |
1,276.98
| 1,028.37 | 248.61 | $200.00 | $49,722.00 |
17 | UNCLASSIFIED EXCAVATION | 4,651.00 | CY |
2,111.73
| 1,740.38 | 371.35 | $135.00 | $50,132.25 |
18 | CRUSHED MISCELLANEOUS BASE | 4,751.00 | CY |
1,840.75
| 1,437.16 | 403.59 | $120.00 | $48,430.80 |
22 | AC PAVEMENT | 643.00 | TON |
384.00
| 324.00 | 60.00 | $110.00 | $6,600.00 |
23 | AC PAVEMENT(PATCH BACK) | 1,008.00 | TON |
167.52
| 159.76 | 7.76 | $200.00 | $1,552.00 |
27 | PCC PAVEMENT | 310.00 | CY |
179.43
| 189.05 | -9.62 | $600.00 | ($5,772.00) |
34 | CURB DRAIN PER STD PLAN 150, N=1, CASE 3 INLET | 16.00 | EA |
9.00
| 7.00 | 2.00 | $500.00 | $1,000.00 |
38 | PCC CURB, TYPE A1-VAR | 516.00 | LF |
516.00
| 466.11 | 49.89 | $36.00 | $1,796.04 |
40 | PCC CURB & GUTTER, TYPE A2-8 | 2,158.00 | LF |
1,898.75
| 1,308.63 | 590.12 | $48.00 | $28,325.76 |
41 | PCC CURB & GUTTER, TYPE A2-VAR | 3,744.00 | LF |
982.75
| 1,229.61 | -246.86 | $49.00 | ($12,096.14) |
42 | PCC CURB & GUTTER, TYPE A2-VAR, W=VAR | 25.00 | LF |
25.00
| 21.00 | 4.00 | $65.00 | $260.00 |
44 | PCC WALK, 4" THICK | 40,585.00 | SF |
18,559.83
| 16,416.00 | 2,143.83 | $10.00 | $21,438.30 |
45 | PCC CURB RAMPS | 461.00 | CY |
206.78
| 188.22 | 18.56 | $1,200.00 | $22,272.00 |
46 | PCC DRIVEWAYS, 6" THICK | 1,697.00 | SF |
1,524.50
| 1,097.28 | 427.22 | $13.00 | $5,553.86 |
47 | DETECTABLE WARNING SURFACE | 3,742.00 | SF |
1,159.50
| 1,069.50 | 90.00 | $40.00 | $3,600.00 |
49 | CROSS GUTTER (MOD) | 143.00 | CY |
43.49
| 51.49 | -8.00 | $700.00 | ($5,600.00) |
55 | ADJUST PULL BOX | 113.00 | EA |
40.00
| 33.00 | 7.00 | $500.00 | $3,500.00 |
93 | TRAFFIC CONTROL | 1.00 | LS |
0.50
| 0.40 | 0.10 | $211,000.00 | $21,100.00 |
|