| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 1 | CONSTRUCTION SCHEDULE (BASELINE) (STIPULATED UNIT PRICE OF $2,500) | 1.00 | LS |
1.00
| 0.00 | 1.00 | $2,500.00 | $2,500.00 |
| 4 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
0.12
| 0.00 | 0.12 | $6,000.00 | $720.00 |
| 5 | PREPARATION OF THE SWPPP (STIPULATED UNIT PRICE OF $5,000) | 1.00 | LS |
1.00
| 0.00 | 1.00 | $5,000.00 | $5,000.00 |
| 6 | IMPLEMENTATION OF THE SWPPP | 1.00 | LS |
0.12
| 0.00 | 0.12 | $32,000.00 | $3,840.00 |
| 7 | OFFICE FACILITIES | 9.00 | MTH |
1.50
| 0.00 | 1.50 | $3,000.00 | $4,500.00 |
| 8 | MOBILIZATION | 1.00 | LS |
0.50
| 0.00 | 0.50 | $846,000.00 | $423,000.00 |
| 15 | CONCRETE REMOVAL (NON-REINFORCED) | 574.00 | CY |
100.75
| 0.00 | 100.75 | $300.00 | $30,225.00 |
| 16 | UNCLASSIFIED EXCAVATION | 825.00 | CY |
452.75
| 0.00 | 452.75 | $240.00 | $108,660.00 |
| 17 | UNCLASSIFIED EXCAVATION (ROADWAY) | 9,513.00 | CY |
95.00
| 0.00 | 95.00 | $80.00 | $7,600.00 |
| 18 | CRUSHED MISCELLANEOUS BASE | 874.00 | CY |
283.00
| 0.00 | 283.00 | $200.00 | $56,600.00 |
| 19 | CSPB MIX DESIGN (STIPULATED UNIT PRICE OF $15,000) | 1.00 | LS |
0.38
| 0.00 | 0.38 | $15,000.00 | $5,700.00 |
| 27 | PCC PAVEMENT | 213.00 | CY |
57.00
| 0.00 | 57.00 | $600.00 | $34,200.00 |
| 31 | CCPRACP MIX DESIGN, SAMPLING, AND TESTING (STIPULATED UNIT PRICE OF $10000) | 1.00 | LS |
0.45
| 0.00 | 0.45 | $10,000.00 | $4,500.00 |
| 37 | PCC CURB & GUTTER, TYPE A2-6 | 617.00 | LF |
25.50
| 0.00 | 25.50 | $72.00 | $1,836.00 |
| 39 | PCC CURB & GUTTER, TYPE A2-VAR | 1,639.00 | LF |
108.50
| 0.00 | 108.50 | $72.00 | $7,812.00 |
| 40 | LONGITUDINAL GUTTER | 30.00 | CY |
10.00
| 0.00 | 10.00 | $890.00 | $8,900.00 |
| 41 | PCC WALK & DRIVEWAYS, 4" THICK | 16,152.00 | SF |
1,149.00
| 0.00 | 1,149.00 | $15.00 | $17,235.00 |
| 42 | PCC CURB RAMPS | 98.00 | CY |
4.50
| 0.00 | 4.50 | $1,800.00 | $8,100.00 |
| 44 | DETECTABLE WARNING SURFACE | 1,050.00 | SF |
78.00
| 0.00 | 78.00 | $56.00 | $4,368.00 |
| 45 | CROSS GUTTER | 41.00 | CY |
14.25
| 0.00 | 14.25 | $850.00 | $12,112.50 |
| 46 | ALLEY INTERSECTION | 21.00 | CY |
10.00
| 0.00 | 10.00 | $900.00 | $9,000.00 |
| 49 | TRAFFIC CONTROL | 1.00 | LS |
0.24
| 0.00 | 0.24 | $473,000.00 | $113,520.00 |
| S-1 | EXTENSION OF TIME (NTP 1) | | DAY |
32.00
| 0.00 | 32.00 | $0.00 | $0.00 |
|