| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 15 | REMOVE EXISTING CHAIN LINK FENCE | 1,730.00 | LF |
1,590.00
| 1,450.00 | 140.00 | $15.00 | $2,100.00 |
| 18 | CONCRETE REMOVAL (REINFORCED) | 1.00 | CY |
11.00
| 1.00 | 10.00 | $1,500.00 | $15,000.00 |
| 28 | AC PAVEMENT | 1,175.00 | TON |
1,265.00
| 1,175.00 | 90.00 | $150.00 | $13,500.00 |
| 31 | PCC PAVEMENT | 20.00 | CY |
36.00
| 20.00 | 16.00 | $650.00 | $10,400.00 |
| 34 | PCC CURB, TYPE A1-8 | 3,076.00 | LF |
3,467.00
| 3,076.00 | 391.00 | $25.00 | $9,775.00 |
| 40 | METAL HAND RAILINGS PER STD PLAN 606 | 169.00 | LF |
170.00
| 169.00 | 1.00 | $175.00 | $175.00 |
| 42 | CHAIN LINK FENCE, 5' HIGH ON TOP OF WALL | 456.00 | LF |
556.00
| 456.00 | 100.00 | $50.00 | $5,000.00 |
| 48 | DETAIL 1 (MODIFIED) (THERMOPLASTIC) | 3,180.00 | LF |
3,197.00
| 3,180.00 | 17.00 | $1.00 | $17.00 |
| 50 | DETAIL 27 (THERMOPLASTIC) | 645.00 | LF |
655.00
| 645.00 | 10.00 | $1.50 | $15.00 |
| 51 | DETAIL 27B (THERMOPLASTIC) | 7,100.00 | LF |
10,127.00
| 7,100.00 | 3,027.00 | $1.00 | $3,027.00 |
| 52 | DETAIL 38 (THERMOPLASTIC) | 350.00 | LF |
354.00
| 350.00 | 4.00 | $1.30 | $5.20 |
| 57 | 24" STRIPING (THERMOPLASTIC) | 1,320.00 | LF |
1,205.00
| 1,188.00 | 17.00 | $8.00 | $136.00 |
| 58 | CURB MARKINGS (ONE-COAT PAINT) | 130.00 | LF |
140.00
| 130.00 | 10.00 | $4.50 | $45.00 |
| 61 | SIGN PANEL | 23.00 | EA |
28.00
| 23.00 | 5.00 | $120.00 | $600.00 |
| 67 | NON-SLIP MATERIAL ON METAL VAULT COVER | 3.00 | EA |
3.00
| 0.00 | 3.00 | $3,500.00 | $10,500.00 |
| S-1 | EXTENSION OF TIME, PART 1 NTP | | DAYS |
15.00
| 0.00 | 15.00 | $0.00 | $0.00 |
| S-4 | CURB MODIFICATIONS | | LS |
1.00
| 0.00 | 1.00 | $31,635.00 | $31,635.00 |
| S-5 | CABLE RAILING AND BOLLARDS | | LS |
1.00
| 0.00 | 1.00 | $28,700.00 | $28,700.00 |
|