| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 1 | CONSTRUCTION SCHEDULE (BASELINE) (STIPULATED UNIT PRICE OF $2,000) | 1.00 | LS |
1.00
| 0.00 | 1.00 | $2,000.00 | $2,000.00 |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 6.00 | MTH |
1.00
| 0.00 | 1.00 | $500.00 | $500.00 |
| 4 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
0.09
| 0.00 | 0.09 | $10,000.00 | $900.00 |
| 5 | IMPLEMENTATION OF BMPS | 1.00 | LS |
0.09
| 0.00 | 0.09 | $35,000.00 | $3,150.00 |
| 6 | OFFICE FACILITIES | 6.00 | MTH |
1.00
| 0.00 | 1.00 | $3,000.00 | $3,000.00 |
| 7 | MOBILIZATION | 1.00 | LS |
0.50
| 0.00 | 0.50 | $274,384.00 | $137,192.00 |
| 8 | CLEARING AND GRUBBING | 1.00 | LS |
0.48
| 0.00 | 0.48 | $356,852.00 | $171,288.96 |
| 13 | TREE REMOVAL (13"-24" DIAMETER) | 20.00 | EA |
16.00
| 0.00 | 16.00 | $2,000.00 | $32,000.00 |
| 14 | TREE REMOVAL (25"+ DIAMETER) | 1.00 | EA |
1.00
| 0.00 | 1.00 | $4,500.00 | $4,500.00 |
| 15 | CONCRETE REMOVAL (NON-REINFORCED) | 472.00 | CY |
11.00
| 0.00 | 11.00 | $404.00 | $4,444.00 |
| 16 | UNCLASSIFIED EXCAVATION | 3,962.00 | CY |
121.00
| 0.00 | 121.00 | $100.00 | $12,100.00 |
| 17 | CRUSHED MISCELLANEOUS BASE | 2,581.00 | CY |
74.00
| 0.00 | 74.00 | $48.00 | $3,552.00 |
| 30 | PCC CURB & GUTTER, TYPE A2-8 | 883.00 | LF |
6.00
| 0.00 | 6.00 | $36.00 | $216.00 |
| 32 | PCC CURB & GUTTER, TYPE A2-VAR | 387.00 | LF |
67.50
| 0.00 | 67.50 | $36.00 | $2,430.00 |
| 34 | PCC WALK & DRIVEWAYS, 4" THICK | 17,446.00 | SF |
3,827.00
| 0.00 | 3,827.00 | $10.00 | $38,270.00 |
| 139 | TRAFFIC CONTROL | 1.00 | LS |
0.09
| 0.00 | 0.09 | $419,835.00 | $37,785.15 |
| S-1 | EXTENSION OF TIME | | DAY |
23.00
| 0.00 | 23.00 | $0.00 | $0.00 |