| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 4 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
0.33
| 0.23 | 0.10 | $6,000.00 | $600.00 |
| 6 | IMPLEMENTATION OF THE SWPPP | 1.00 | LS |
0.33
| 0.23 | 0.10 | $32,000.00 | $3,200.00 |
| 7 | OFFICE FACILITIES | 9.00 | MTH |
3.50
| 2.50 | 1.00 | $3,000.00 | $3,000.00 |
| 15 | CONCRETE REMOVAL (NON-REINFORCED) | 574.00 | CY |
323.25
| 209.20 | 114.05 | $300.00 | $34,215.00 |
| 16 | UNCLASSIFIED EXCAVATION | 825.00 | CY |
742.75
| 581.50 | 161.25 | $240.00 | $38,700.00 |
| 17 | UNCLASSIFIED EXCAVATION (ROADWAY) | 9,513.00 | CY |
285.00
| 190.26 | 94.74 | $80.00 | $7,579.20 |
| 18 | CRUSHED MISCELLANEOUS BASE | 874.00 | CY |
573.10
| 409.55 | 163.55 | $200.00 | $32,710.00 |
| 24 | TEMPORARY AC PAVEMENT (PATCH BACK) | 241.00 | TON |
90.59
| 74.50 | 16.09 | $230.00 | $3,700.70 |
| 37 | PCC CURB & GUTTER, TYPE A2-6 | 617.00 | LF |
601.50
| 586.50 | 15.00 | $72.00 | $1,080.00 |
| 39 | PCC CURB & GUTTER, TYPE A2-VAR | 1,639.00 | LF |
1,296.50
| 774.00 | 522.50 | $72.00 | $37,620.00 |
| 41 | PCC WALK & DRIVEWAYS, 4" THICK | 16,152.00 | SF |
11,223.35
| 5,387.75 | 5,835.60 | $15.00 | $87,534.00 |
| 42 | PCC CURB RAMPS | 98.00 | CY |
62.85
| 26.60 | 36.25 | $1,800.00 | $65,250.00 |
| 44 | DETECTABLE WARNING SURFACE | 1,050.00 | SF |
663.00
| 318.00 | 345.00 | $56.00 | $19,320.00 |
| 45 | CROSS GUTTER | 41.00 | CY |
29.05
| 14.25 | 14.80 | $850.00 | $12,580.00 |
| 48 | NO. 6 PULL BOX INCL PCC COVER | 4.00 | EA |
4.00
| 0.00 | 4.00 | $500.00 | $2,000.00 |
| 49 | TRAFFIC CONTROL | 1.00 | LS |
0.52
| 0.32 | 0.20 | $473,000.00 | $94,600.00 |