| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 6.00 | MTH |
2.00
| 1.00 | 1.00 | $500.00 | $500.00 |
| 4 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
0.24
| 0.09 | 0.15 | $10,000.00 | $1,500.00 |
| 5 | IMPLEMENTATION OF BMPS | 1.00 | LS |
0.24
| 0.09 | 0.15 | $35,000.00 | $5,250.00 |
| 6 | OFFICE FACILITIES | 6.00 | MTH |
2.00
| 1.00 | 1.00 | $3,000.00 | $3,000.00 |
| 7 | MOBILIZATION | 1.00 | LS |
0.75
| 0.50 | 0.25 | $274,384.00 | $68,596.00 |
| 8 | CLEARING AND GRUBBING | 1.00 | LS |
0.96
| 0.48 | 0.48 | $356,852.00 | $171,288.96 |
| 11 | ROOT PRUNE TREE (INCL ROOT CONTROL BARRIER) | 6.00 | EA |
4.00
| 0.00 | 4.00 | $1,100.00 | $4,400.00 |
| 13 | TREE REMOVAL (13"-24" DIAMETER) | 20.00 | EA |
19.00
| 16.00 | 3.00 | $2,000.00 | $6,000.00 |
| 15 | CONCRETE REMOVAL (NON-REINFORCED) | 472.00 | CY |
62.75
| 11.00 | 51.75 | $404.00 | $20,907.00 |
| 16 | UNCLASSIFIED EXCAVATION | 3,962.00 | CY |
233.10
| 121.00 | 112.10 | $100.00 | $11,210.00 |
| 17 | CRUSHED MISCELLANEOUS BASE | 2,581.00 | CY |
153.00
| 74.00 | 79.00 | $48.00 | $3,792.00 |
| 28 | PCC CURB & GUTTER, TYPE A2-6, W=1' | 80.00 | LF |
52.20
| 0.00 | 52.20 | $32.00 | $1,670.40 |
| 30 | PCC CURB & GUTTER, TYPE A2-8 | 883.00 | LF |
41.50
| 6.00 | 35.50 | $36.00 | $1,278.00 |
| 34 | PCC WALK & DRIVEWAYS, 4" THICK | 17,446.00 | SF |
9,120.25
| 3,827.00 | 5,293.25 | $10.00 | $52,932.50 |
| 139 | TRAFFIC CONTROL | 1.00 | LS |
0.24
| 0.09 | 0.15 | $419,835.00 | $62,975.25 |
| 141 | CHANGEABLE MESSAGE SIGN | 6.00 | EA |
2.00
| 0.00 | 2.00 | $13,000.00 | $26,000.00 |
|