Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 8.00 | MTH |
8.00
| 7.00 | 1.00 | $500.00 | $500.00 |
5 | IMPLEMENTATION OF THE SWPPP | 1.00 | LS |
0.80
| 0.70 | 0.10 | $23,000.00 | $2,300.00 |
6 | OFFICE FACILITIES | 9.00 | MTH |
8.00
| 7.00 | 1.00 | $2,600.00 | $2,600.00 |
15 | CONCRETE REMOVAL (NON-REINFORCED) | 3,146.00 | CY |
2,159.90
| 1,766.67 | 393.23 | $200.00 | $78,646.00 |
17 | UNCLASSIFIED EXCAVATION | 4,651.00 | CY |
3,596.00
| 3,054.36 | 541.64 | $135.00 | $73,121.40 |
18 | CRUSHED MISCELLANEOUS BASE | 4,751.00 | CY |
3,291.00
| 2,648.87 | 642.13 | $120.00 | $77,055.60 |
22 | AC PAVEMENT | 643.00 | TON |
495.87
| 437.51 | 58.36 | $110.00 | $6,419.60 |
23 | AC PAVEMENT(PATCH BACK) | 1,008.00 | TON |
349.35
| 307.17 | 42.18 | $200.00 | $8,436.00 |
27 | PCC PAVEMENT | 310.00 | CY |
204.62
| 179.43 | 25.19 | $600.00 | $15,114.00 |
39 | PCC CURB & GUTTER, TYPE A2-6 | 469.00 | LF |
81.00
| 73.35 | 7.65 | $47.00 | $359.55 |
41 | PCC CURB & GUTTER, TYPE A2-VAR | 3,744.00 | LF |
2,658.35
| 2,151.21 | 507.14 | $49.00 | $24,849.86 |
44 | PCC WALK, 4" THICK | 40,585.00 | SF |
35,794.00
| 29,488.27 | 6,305.73 | $10.00 | $63,057.30 |
45 | PCC CURB RAMPS | 461.00 | CY |
397.30
| 317.79 | 79.51 | $1,200.00 | $95,412.00 |
47 | DETECTABLE WARNING SURFACE | 3,742.00 | SF |
2,360.18
| 1,835.43 | 524.75 | $40.00 | $20,990.00 |
49 | CROSS GUTTER (MOD) | 143.00 | CY |
134.17
| 66.57 | 67.60 | $700.00 | $47,320.00 |
55 | ADJUST PULL BOX | 113.00 | EA |
96.00
| 70.00 | 26.00 | $500.00 | $13,000.00 |
93 | TRAFFIC CONTROL | 1.00 | LS |
0.80
| 0.70 | 0.10 | $211,000.00 | $21,100.00 |
S-3 | TRAFFIC SIGNAL COMPONENTS | | T&M |
551,880.50
| 529,142.99 | 22,737.51 | $1.00 | $22,737.51 |
S-5 | PHOTOCOPIER RENTAL | | T&M |
1,012.78
| 0.00 | 1,012.78 | $1.00 | $1,012.78 |
|