Los Angeles County Public Works
Project Management Division III
Progress Payment 8
Project Name: Project No. 5241 - Reinforced Concrete Box Reconstruction
Contractor: GMZ Engineering, Inc.
5655 Lindero Canyon Road #430
Westlake Village, CA 91362
Project ID: FCC0001319
Federal Number(s): None
Original Contract: $8,032,540.00
Awarded: 4/17/2023
Period Ending: 4/20/2024
Board Accepted: 5/13/2025
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
17CONCRETE REMOVAL (REINFORCED)525.00CY 569.00 505.0064.00$1,000.00$64,000.00
18UNCLASSIFIED EXCAVATION9,200.00CY 9,200.00 8,294.00906.00$85.00$77,010.00
2511' - 0" W X 9' - 2" H RCB PER SECTION B1-A, SHEET 4292.00CY 340.00 298.0042.00$3,600.00$151,200.00
S-9COFFERDAM FLOODING LS 1.00 0.001.00$50,000.00$50,000.00
S-10COFFERDAM ACCESS RAMPS LS 1.00 0.001.00$72,000.00$72,000.00
S-11POSTPONE WAVE BARRIER INSTALLATION NWD 134.00 0.00134.00$0.00$0.00
S-12GROUT PRECAST GAP LS 1.00 0.001.00$25,000.00$25,000.00
S-13ADDITIONAL UNCLASSIFIED EXCAVATION LS 1.00 0.001.00$50,000.00$50,000.00

DEDUCTION DETAIL

There are NO deductions this period

FINANCIAL SUMMARY

  Total Previous Current
Earned $8,662,650.00 $8,173,440.00 $489,210.00
Retained $433,132.50 $408,672.00 $24,460.50
Deducted $0.00 $0.00 $0.00
Due $8,229,517.50 $7,764,768.00 $464,749.50



Contact Office Engineer
Contractor Copy  
P Please consider the environment before printing this report.