| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 17 | CONCRETE REMOVAL (REINFORCED) | 525.00 | CY |
569.00
| 505.00 | 64.00 | $1,000.00 | $64,000.00 |
| 18 | UNCLASSIFIED EXCAVATION | 9,200.00 | CY |
9,200.00
| 8,294.00 | 906.00 | $85.00 | $77,010.00 |
| 25 | 11' - 0" W X 9' - 2" H RCB PER SECTION B1-A, SHEET 4 | 292.00 | CY |
340.00
| 298.00 | 42.00 | $3,600.00 | $151,200.00 |
| S-9 | COFFERDAM FLOODING | | LS |
1.00
| 0.00 | 1.00 | $50,000.00 | $50,000.00 |
| S-10 | COFFERDAM ACCESS RAMPS | | LS |
1.00
| 0.00 | 1.00 | $72,000.00 | $72,000.00 |
| S-11 | POSTPONE WAVE BARRIER INSTALLATION | | NWD |
134.00
| 0.00 | 134.00 | $0.00 | $0.00 |
| S-12 | GROUT PRECAST GAP | | LS |
1.00
| 0.00 | 1.00 | $25,000.00 | $25,000.00 |
| S-13 | ADDITIONAL UNCLASSIFIED EXCAVATION | | LS |
1.00
| 0.00 | 1.00 | $50,000.00 | $50,000.00 |