Los Angeles County Public Works
Project Management Division III
Progress Payment 1
Project Name: Saybrook Medians Phase III
Contractor: Marina Landscape, Inc.
3707 West Garden Grove Boulevard
Orange, CA 92868
Project ID: RDC0016557
Federal Number(s): None
Original Contract: $1,501,240.70
Awarded: 2/2/2024
Period Ending: 6/4/2024
Board Accepted: 6/11/2025
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
1CONSTRUCTION SCHEDULE (BASELINE) (STIPULATED UNIT PRICE OF $2,500)1.00LS 1.00 0.001.00$2,500.00$2,500.00
2CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH)4.00MTH 1.00 0.001.00$500.00$500.00
5PREPARATION OF THE SWPPP (STIPULATED UNIT PRICE OF $5,000)1.00LS 1.00 0.001.00$5,000.00$5,000.00
6IMPLEMENTATION OF THE SWPPP1.00LS 0.25 0.000.25$25,000.00$6,250.00
7OFFICE FACILITIES5.00MTH 1.00 0.001.00$5,500.00$5,500.00
9CLEARING AND GRUBBING123,451.00SF 71,272.00 0.0071,272.00$0.70$49,890.40
10UNCLASSIFIED EXCAVATION1,809.00CY 436.00 0.00436.00$72.00$31,392.00
11UTILITY POTHOLES6.00EA 4.00 0.004.00$1,000.00$4,000.00
12TRAFFIC CONTROL1.00LS 0.25 0.000.25$20,000.00$5,000.00
16LANDSCAPING1.00LS 0.15 0.000.15$253,000.00$37,950.00
18IRRIGATION SYSTEM1.00LS 0.15 0.000.15$252,000.00$37,800.00

DEDUCTION DETAIL

There are NO deductions this period

FINANCIAL SUMMARY

  Total Previous Current
Earned $185,782.40 $0.00 $185,782.40
Retained $9,289.12 $0.00 $9,289.12
Deducted $0.00 $0.00 $0.00
Due $176,493.28 $0.00 $176,493.28