| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 1 | CONSTRUCTION SCHEDULE (BASELINE) (STIPULATED UNIT PRICE OF $2,500) | 1.00 | LS |
1.00
| 0.00 | 1.00 | $2,500.00 | $2,500.00 |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 4.00 | MTH |
1.00
| 0.00 | 1.00 | $500.00 | $500.00 |
| 5 | PREPARATION OF THE SWPPP (STIPULATED UNIT PRICE OF $5,000) | 1.00 | LS |
1.00
| 0.00 | 1.00 | $5,000.00 | $5,000.00 |
| 6 | IMPLEMENTATION OF THE SWPPP | 1.00 | LS |
0.25
| 0.00 | 0.25 | $25,000.00 | $6,250.00 |
| 7 | OFFICE FACILITIES | 5.00 | MTH |
1.00
| 0.00 | 1.00 | $5,500.00 | $5,500.00 |
| 9 | CLEARING AND GRUBBING | 123,451.00 | SF |
71,272.00
| 0.00 | 71,272.00 | $0.70 | $49,890.40 |
| 10 | UNCLASSIFIED EXCAVATION | 1,809.00 | CY |
436.00
| 0.00 | 436.00 | $72.00 | $31,392.00 |
| 11 | UTILITY POTHOLES | 6.00 | EA |
4.00
| 0.00 | 4.00 | $1,000.00 | $4,000.00 |
| 12 | TRAFFIC CONTROL | 1.00 | LS |
0.25
| 0.00 | 0.25 | $20,000.00 | $5,000.00 |
| 16 | LANDSCAPING | 1.00 | LS |
0.15
| 0.00 | 0.15 | $253,000.00 | $37,950.00 |
| 18 | IRRIGATION SYSTEM | 1.00 | LS |
0.15
| 0.00 | 0.15 | $252,000.00 | $37,800.00 |