| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 1 | CONSTRUCTION SCHEDULE (BASELINE) (STIPULATED UNIT PRICE OF $2,500) | 1.00 | LS |
1.00
| 0.00 | 1.00 | $2,500.00 | $2,500.00 |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 4.00 | MTH |
1.00
| 0.00 | 1.00 | $2,000.00 | $2,000.00 |
| 4 | PREPARATION OF THE SWPPP (STIPULATED UNIT PRICE OF $5,000) | 1.00 | LS |
1.00
| 0.00 | 1.00 | $5,000.00 | $5,000.00 |
| 5 | IMPLEMENTATION OF THE SWPPP | 1.00 | LS |
0.20
| 0.00 | 0.20 | $28,000.00 | $5,600.00 |
| 6 | IMPLEMENTATION OF LTWHP | 1.00 | LS |
0.20
| 0.00 | 0.20 | $7,700.00 | $1,540.00 |
| 7 | OFFICE FACILITIES | 5.00 | MTH |
1.00
| 0.00 | 1.00 | $25,000.00 | $25,000.00 |
| 8 | MOBILIZATION | 1.00 | LS |
0.50
| 0.00 | 0.50 | $750,000.00 | $375,000.00 |
| 9 | CLEARING AND GRUBBING | 1.00 | LS |
0.20
| 0.00 | 0.20 | $300,000.00 | $60,000.00 |
| 10 | CONCRETE REMOVAL (NON-REINFORCED) | 345.00 | CY |
167.17
| 0.00 | 167.17 | $300.00 | $50,151.00 |
| 11 | UNCLASSIFIED EXCAVATION | 5,029.00 | CY |
204.80
| 0.00 | 204.80 | $80.00 | $16,384.00 |
| 18 | RECONSTRUCT MANHOLE | 100.00 | EA |
9.00
| 0.00 | 9.00 | $2,525.00 | $22,725.00 |
| 23 | PCC CURB & GUTTER, TYPE A2-8 | 426.00 | LF |
202.00
| 0.00 | 202.00 | $84.00 | $16,968.00 |
| 24 | PCC WALK, 4" THICK | 805.00 | SF |
782.00
| 0.00 | 782.00 | $20.00 | $15,640.00 |
| 25 | CROSS GUTTER | 147.00 | CY |
147.00
| 0.00 | 147.00 | $705.00 | $103,635.00 |
| 26 | CRUSHED MISCELLANEOUS BASE | 452.00 | CY |
145.96
| 0.00 | 145.96 | $122.00 | $17,807.12 |
| 32 | PCC WALK & DRIVEWAYS, 4" THICK | 12,180.00 | SF |
2,620.25
| 0.00 | 2,620.25 | $13.00 | $34,063.25 |
| 33 | TRAFFIC CONTROL | 1.00 | LS |
0.20
| 0.00 | 0.20 | $362,000.43 | $72,400.09 |
|