Los Angeles County Public Works
Project Management Division III
As-Built 6
Project Name: Rosemead Boulevard Interim Complete Streets
Contractor: Los Angeles Engineering, Inc.
633 North Barranca Avenue
Covina, CA 91723
Project ID: RDC0016284
Federal Number(s): None
Original Contract: $2,699,500.00
Awarded: 3/13/2023
Period Ending: 5/8/2024
Board Accepted: 6/5/2024
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
1CONSTRUCTION SCHEDULE (BASELINE) (STIPULATED UNIT PRICE OF $2,500)1.00LS 1.00 1.000.00$2,500.00$0.00
2CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH)3.00MTH 3.00 3.000.00$1,500.00$0.00
3CONSTRUCTION SCHEDULE (AS-BUILT) (STIPULATED UNIT PRICE OF $1,000)1.00LS 1.00 1.000.00$1,000.00$0.00
4IMPLEMENTATION OF THE LTWHP1.00LS 1.00 1.000.00$15,000.00$0.00
5PREPARATION OF THE SWPPP (STIPULATED UNIT PRICE OF $5,000)1.00LS 1.00 1.000.00$5,000.00$0.00
6IMPLEMENTATION OF THE SWPPP1.00LS 1.00 1.000.00$25,000.00$0.00
7PREPARATION OF THE DIVERSION OF WATER PLAN (STIPULATED UNIT PRICE OF $5,000)1.00LS 1.00 1.000.00$5,000.00$0.00
8IMPLEMENTATION OF THE DIVERSION OF WATER PLAN1.00LS 1.00 1.000.00$75,000.00$0.00
9SHORING OF OPEN EXCAVATIONS1.00LS 1.00 1.000.00$284,711.00$0.00
10OFFICE FACILITIES4.00MTH 4.00 4.000.00$3,000.00$0.00
11MOBILIZATION1.00LS 1.00 1.000.00$270,000.00$0.00
12CLEARING AND GRUBBING1.00LS 1.00 1.000.00$74,500.00$0.00
13TREE REMOVAL (13"-24" DIAMETER)1.00EA 1.00 1.000.00$4,000.00$0.00
14TREE REMOVAL (25"+ DIAMETER)1.00EA 2.00 2.000.00$8,000.00$0.00
15REMOVE EXISTING CHAIN LINK FENCE1,730.00LF 1,590.00 1,590.000.00$15.00$0.00
16REMOVE AND DISPOSE CHAIN LINK GATE2.00EA 2.00 2.000.00$900.00$0.00
17CONCRETE REMOVAL (NON-REINFORCED)96.00CY 142.00 142.000.00$125.00$0.00
18CONCRETE REMOVAL (REINFORCED)1.00CY 11.00 11.000.00$1,500.00$0.00
19REMOVE AND DISPOSE BOLLARD1.00EA 1.00 1.000.00$250.00$0.00
20REMOVE 18 " CSP58.00LF 58.00 58.000.00$50.00$0.00
21UNCLASSIFIED EXCAVATION1,881.00CY 1,881.00 1,881.000.00$160.00$0.00
22STRUCTURE EXCAVATION (RETAINING WALL)1,706.00CY 1,706.00 1,706.000.00$85.00$0.00
23STRUCTURE BACKFILL (RETAINING WALL)1,457.00CY 1,457.00 1,457.000.00$75.00$0.00
24CRUSHED MISCELLANEOUS BASE135.00CY 135.00 135.000.00$160.00$0.00
25COLD MILL AC PAVEMENT (0 - 1-1/2")13,133.00SF 13,133.00 13,133.000.00$2.00$0.00
26AC CURB, TYPE D1-858.00LF 58.00 58.000.00$60.00$0.00
27AC CURB, TYPE D1-VAR28.00LF 28.00 28.000.00$60.00$0.00
28AC PAVEMENT1,175.00TON 1,265.00 1,265.000.00$150.00$0.00
29AC PAVEMENT(PATCH BACK)69.00TON 69.00 69.000.00$350.00$0.00
30AC PAVEMENT(DRIVEWAYS)24.00TON 24.00 24.000.00$400.00$0.00
31PCC PAVEMENT20.00CY 36.00 36.000.00$650.00$0.00
32REINFORCED CONCRETE RETAINING WALL TYPE 6 - CALTRANS294.00CY 296.00 296.000.00$1,450.00$0.00
33PCC CURB, TYPE A1-635.00LF 35.00 35.000.00$130.00$0.00
34PCC CURB, TYPE A1-83,076.00LF 3,467.00 3,467.000.00$25.00$0.00
35PCC CURB, TYPE A1-MOD2,247.00LF 2,247.00 2,247.000.00$17.00$0.00
36PCC WALK, 4" THICK919.00SF 919.00 919.000.00$9.00$0.00
37PCC CURB RAMPS7.00CY 7.00 7.000.00$2,200.00$0.00
38CASE CM CURB RAMP1.00EA 1.00 1.000.00$5,500.00$0.00
39DETECTABLE WARNING SURFACE140.00SF 140.00 140.000.00$40.00$0.00
40METAL HAND RAILINGS PER STD PLAN 606169.00LF 170.00 170.000.00$175.00$0.00
41CHAIN LINK FENCE, 5' HIGH1,284.00LF 1,284.00 1,284.000.00$50.00$0.00
42CHAIN LINK FENCE, 5' HIGH ON TOP OF WALL456.00LF 556.00 556.000.00$50.00$0.00
43ROLLING CHAIN LINK GATE2.00EA 2.00 2.000.00$10,000.00$0.00
44TRANSPORTATION AND DISPOSAL OF TREATED WOOD WASTE9,370.00LB 9,370.00 9,370.000.00$1.00$0.00
4518" RCP, 2500 D65.00LF 65.00 65.000.00$300.00$0.00
46FILTRATION TRENCH1,856.00LF 2,247.00 2,247.000.00$78.00$0.00
47INDUCTIVE LOOP DETECTOR AND LEADS SAW CUT1,239.00LF 1,239.00 1,239.000.00$15.00$0.00
48DETAIL 1 (MODIFIED) (THERMOPLASTIC)3,180.00LF 3,197.00 3,197.000.00$1.00$0.00
49DETAIL 9 (THERMOPLASTIC)880.00LF 496.00 496.000.00$0.80$0.00
50DETAIL 27 (THERMOPLASTIC)645.00LF 655.00 655.000.00$1.50$0.00
51DETAIL 27B (THERMOPLASTIC)7,100.00LF 10,127.00 10,127.000.00$1.00$0.00
52DETAIL 38 (THERMOPLASTIC)350.00LF 354.00 354.000.00$1.30$0.00
53PAVEMENT MARKINGS (THERMOPLASTIC)177.00SF 45.00 45.000.00$9.00$0.00
544" STRIPING (THERMOPLASTIC)105.00LF 0.00 0.000.00$0.60$0.00
558" STRIPING (THERMOPLASTIC)635.00LF 622.00 622.000.00$1.20$0.00
5612" STRIPING (THERMOPLASTIC)200.00LF 192.00 192.000.00$4.00$0.00
5724" STRIPING (THERMOPLASTIC)1,320.00LF 1,205.00 1,205.000.00$8.00$0.00
58CURB MARKINGS (ONE-COAT PAINT)130.00LF 140.00 140.000.00$4.50$0.00
59REMOVE PAVEMENT MARKINGS (THERMOPLASTIC)45.00SF 45.00 45.000.00$2.20$0.00
60REMOVE STRIPING (THERMOPLASTIC)4,401.00LF 2,156.00 2,156.000.00$1.50$0.00
61SIGN PANEL23.00EA 28.00 28.000.00$120.00$0.00
62RELOCATE SIGN10.00EA 9.00 9.000.00$100.00$0.00
63REMOVE SIGN4.00EA 2.00 2.000.00$60.00$0.00
64RELOCATE SIGN POST9.00EA 9.00 9.000.00$220.00$0.00
65SIGN POST (ROADSIDE SIGN)9.00EA 9.00 9.000.00$350.00$0.00
66TRAFFIC CONTROL1.00LS 1.00 1.000.00$75,000.00$0.00
67NON-SLIP MATERIAL ON METAL VAULT COVER3.00EA 3.00 3.000.00$3,500.00$0.00
S-1EXTENSION OF TIME, PART 1 NTP DAYS 15.00 15.000.00$0.00$0.00
S-2ADD ADDITIONAL REBARS LS 1.00 1.000.00$4,000.00$0.00
S-4CURB MODIFICATIONS LS 1.00 1.000.00$31,635.00$0.00
S-5CABLE RAILING AND BOLLARDS LS 1.00 1.000.00$28,700.00$0.00

DEDUCTION DETAIL

DescriptionUnitTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
OVERTIME INSPECTIONHOUR 0.00 0.000.00$100.00 $0.00
LIQUIDATED DAMAGESDAY 0.00 0.000.00$2,000.00 $0.00
LABOR COMPLIANCEVIOLATION 0.00 0.000.00$250.00 $0.00
AFFIRMATIVE ACTIONVIOLATION 0.00 0.000.00$200.00 $0.00
BEST MANAGEMENT PRACTICEVIOLATION 0.00 0.000.00$1,000.00 $0.00
SCHEDULE UPDATEMONTHLY 0.00 0.000.00$250.00 $0.00
LOCAL TARGATED WORKER HIRING PROGRAMSTIP 0.00 0.000.00$1.00 $0.00

FINANCIAL SUMMARY

  Total Previous Current
Earned $2,860,328.90 $2,860,328.90 $0.00
Retained* $93,923.47 $93,923.47 $0.00
Deducted $0.00 $0.00 $0.00
Due $2,766,405.43 $2,766,405.43 $0.00



*The term "As-Built" used by the Department of Public Works in combination with the Engineer's Monthly Estimate process indicates that the project has been field accepted and that the pay quantities and deductions as detailed above are FINAL. Unless a certified letter is received by this office within 14 calendar days disputing the amounts shown, an acceptance letter will be filed with the Board of Supervisors authorizing the release of retention.

*This project has an escrow account.