| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 4 | MOBILIZATION | 1.00 | LS |
0.50
| 0.00 | 0.50 | $141,250.00 | $70,625.00 |
| 5 | IMPLEMENTATION OF BMPS | 1.00 | LS |
0.18
| 0.09 | 0.09 | $10,000.00 | $900.00 |
| 6 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
0.18
| 0.09 | 0.09 | $5,000.00 | $450.00 |
| 7 | EXPLORATORY EXCAVATION OF UTILITIES (ALLOWANCE OF $18,750) | 18,750.00 | AL |
9,800.00
| 0.00 | 9,800.00 | $1.00 | $9,800.00 |
| 21 | 2" CONDUIT (SCH 80 PVC) | 140.00 | LF |
44.00
| 0.00 | 44.00 | $100.00 | $4,400.00 |
| 22 | 3" CONDUIT (SCH 80 PVC) | 1,115.00 | LF |
390.00
| 0.00 | 390.00 | $95.00 | $37,050.00 |
| 23 | 4" CONDUIT (SCH 80 PVC) | 270.00 | LF |
110.00
| 0.00 | 110.00 | $110.00 | $12,100.00 |
| 31 | REMOVE PULL BOX AND RESURFACE SIDEWALK | 10.00 | EA |
9.00
| 0.00 | 9.00 | $2,400.00 | $21,600.00 |
| 33 | TYPE III PULL BOX | 37.00 | EA |
18.00
| 0.00 | 18.00 | $1,100.00 | $19,800.00 |
| 132 | TRAFFIC CONTROL | 1.00 | LS |
0.18
| 0.00 | 0.18 | $88,884.00 | $15,999.12 |
| 133 | FLASHING ARROW SIGN | 2.00 | EA |
2.00
| 0.00 | 2.00 | $6,000.00 | $12,000.00 |