Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 4.00 | MTH |
2.00
| 1.00 | 1.00 | $2,000.00 | $2,000.00 |
5 | IMPLEMENTATION OF THE SWPPP | 1.00 | LS |
0.40
| 0.20 | 0.20 | $28,000.00 | $5,600.00 |
6 | IMPLEMENTATION OF LTWHP | 1.00 | LS |
0.40
| 0.20 | 0.20 | $7,700.00 | $1,540.00 |
7 | OFFICE FACILITIES | 5.00 | MTH |
2.00
| 1.00 | 1.00 | $25,000.00 | $25,000.00 |
8 | MOBILIZATION | 1.00 | LS |
0.95
| 0.50 | 0.45 | $750,000.00 | $337,500.00 |
9 | CLEARING AND GRUBBING | 1.00 | LS |
0.40
| 0.20 | 0.20 | $300,000.00 | $60,000.00 |
11 | UNCLASSIFIED EXCAVATION | 5,029.00 | CY |
2,550.80
| 204.80 | 2,346.00 | $80.00 | $187,680.00 |
12 | CEMENT STABILIZED PULVERIZED BASE, 8" THICK | 105,279.00 | SY |
26,931.00
| 0.00 | 26,931.00 | $9.00 | $242,379.00 |
13 | PORTLAND CEMENT FOR CSPB | 2,060.00 | TON |
220.56
| 0.00 | 220.56 | $256.00 | $56,463.36 |
14 | PRIME/TACK COAT FOR CSPB | 21,058.00 | GAL |
4,339.00
| 0.00 | 4,339.00 | $8.00 | $34,712.00 |
15 | COLD MILL AC PAVEMENT (> 1-1/2 - 3") | 690,598.00 | SF |
308,003.00
| 0.00 | 308,003.00 | $0.36 | $110,881.08 |
16 | COLD MILL AC PAVEMENT (> 3") | 256,922.00 | SF |
172,166.00
| 0.00 | 172,166.00 | $0.57 | $98,134.62 |
21 | COLD CENTRAL PLANT RECYCLED ASPHALT CONCRETE PAVEMENT, 2.5" THICK | 105,279.00 | SY |
26,931.00
| 0.00 | 26,931.00 | $12.25 | $329,904.75 |
22 | EMULSIFIED RECYCLING AGENT | 452.00 | TON |
107.58
| 0.00 | 107.58 | $832.00 | $89,506.56 |
31 | PORTLAND CEMENT FOR CCPRACP | 127.00 | TON |
17.53
| 0.00 | 17.53 | $250.00 | $4,382.50 |
33 | TRAFFIC CONTROL | 1.00 | LS |
0.40
| 0.20 | 0.20 | $362,000.43 | $72,400.09 |
S-2 | DAMAGED LIGHTING WIRE REPAIR | | LS |
1.00
| 0.00 | 1.00 | $6,900.00 | $6,900.00 |
|