| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 1 | CONSTRUCTION SCHEDULE (BASELINE) (STIPULATED UNIT PRICE OF $2,500) | 1.00 | LS |
1.00
| 0.00 | 1.00 | $2,500.00 | $2,500.00 |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 4.00 | MTH |
1.00
| 0.00 | 1.00 | $500.00 | $500.00 |
| 4 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
0.25
| 0.00 | 0.25 | $15,000.00 | $3,750.00 |
| 5 | IMPLEMENTATION OF BMPS | 1.00 | LS |
0.25
| 0.00 | 0.25 | $45,000.00 | $11,250.00 |
| 6 | PREPARATION OF THE NOISE MITIGATION PLAN (STIPULATED UNIT PRICE OF $2,500) | 1.00 | LS |
1.00
| 0.00 | 1.00 | $2,500.00 | $2,500.00 |
| 7 | CONSTRUCTION OF TEMPORARY SOUND BARRIER | 60.00 | LF |
60.00
| 0.00 | 60.00 | $250.00 | $15,000.00 |
| 8 | MAINTENANCE OF TEMPORARY SOUND BARRIER | 60.00 | LF |
15.00
| 0.00 | 15.00 | $30.00 | $450.00 |
| 10 | PREPARATION OF THE COFFERDAM DEWATERING PLAN (STIPULATED UNIT PRICE OF $5,000) | 1.00 | LS |
1.00
| 0.00 | 1.00 | $5,000.00 | $5,000.00 |
| 12 | PREPARATION OF THE SPILL PREVENTION AND CONTROL PLAN (STIPULATED UNIT PRICE OF $2,500) | 1.00 | LS |
1.00
| 0.00 | 1.00 | $2,500.00 | $2,500.00 |
| 13 | PREPARATION OF SITE-SPECIFIC HEALTH AND SAFETY PLAN (STIPULATED UNIT PRICE OF $10,000) | 1.00 | LS |
1.00
| 0.00 | 1.00 | $10,000.00 | $10,000.00 |
| 14 | IMPLEMENTATION OF THE SITE-SPECIFIC HEALTH AND SAFETY PLAN | 1.00 | LS |
0.25
| 0.00 | 0.25 | $15,000.00 | $3,750.00 |
| 15 | PREPARATION OF TWW WORKPLAN (STIPULATED UNIT PRICE OF $2,500) | 1.00 | LS |
1.00
| 0.00 | 1.00 | $2,500.00 | $2,500.00 |
| 17 | PREPARATION OF THE SITE-SPECIFIC LEAD COMPLIANCE PLAN (STIPULATED UNIT PRICE OF $3,000) | 1.00 | LS |
1.00
| 0.00 | 1.00 | $3,000.00 | $3,000.00 |
| 20 | PREPARATION OF THE SITE-SPECIFIC ASBESTOS ABATEMENT PLAN (STIPULATED UNIT PRICE OF $3,000) | 1.00 | LS |
1.00
| 0.00 | 1.00 | $3,000.00 | $3,000.00 |
| 24 | OFFICE FACILITIES | 4.00 | MTH |
1.00
| 0.00 | 1.00 | $3,500.00 | $3,500.00 |
| 25 | MOBILIZATION | 1.00 | LS |
0.75
| 0.00 | 0.75 | $323,600.00 | $242,700.00 |
| 26 | FRP GRATING | 1.00 | LS |
0.50
| 0.00 | 0.50 | $3,600.00 | $1,800.00 |
| 32 | CONSTRUCT AND REMOVE COFFERDAM | 1.00 | EA |
0.40
| 0.00 | 0.40 | $1,639,519.00 | $655,807.60 |
| 47 | TEMPORARY BOATYARD | 1.00 | LS |
0.42
| 0.00 | 0.42 | $67,580.00 | $28,383.60 |
| 52 | STEEL PIPE MANIFOLD | 1.00 | LS |
0.28
| 0.00 | 0.28 | $134,000.00 | $37,520.00 |
| 60 | STEEL PIPES REMOVAL | 1.00 | LS |
0.34
| 0.00 | 0.34 | $39,850.00 | $13,549.00 |
| 63 | ELECTRICAL WORK | 1.00 | LS |
0.13
| 0.00 | 0.13 | $527,783.00 | $68,611.79 |
| S-3 | PREAST REINFORCED SLAB CHANGES | | LS |
1.00
| 0.00 | 1.00 | $3,315.00 | $3,315.00 |
| S-4 | EXTENSION OF TIME, PART 1 NTP | | WD |
35.00
| 0.00 | 35.00 | $0.00 | $0.00 |
|